COPA page Banner.
                               

CALL (812) 333-8888 FOR MORE INFORMATION OR E-MAIL info@copa.org

                             

Library: Rulings: Foster Report

                               
 

REPORT AND RECOMMENDATIONS
of the Magistrate Judge and Special Master
Jan 20, 1999 .


In the
United Sates District Court
for Southern District of Indiana
Indianapolis Division
UNITED STATES OF AMERICA,
Plaintiff,


The STATE OF INDIANA and the INDIANA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT,

Intervening plaintiffs,

vs.

CBS CORPORATION, f/k/a WestinghouseElectric Corporation,

Defendant.

The CITY OF BLOOMINGTON, INDIANA; The UTILITIES SERVICE BOARD OF BLOOMINGTON, INDIANA; and MONROE COUNTY, INDIANA,

Plaintiffs,

vs.

CBS CORPORATION, f/k/a Westinghouse Corporation, and MONSANTO COMPANY,Defendants.

REPORT AND RECOMMENDATIONS

of the Magistrate Judge and Special Master.


By order of November 21, 1997, the Court appointed this magistrate judge to serve as a Special Master "to see that the aims of the consent decree, as modified by the orders of the Court, are carried out expeditiously and to resolve possible disputes between the parties." Pursuant to Rule 53 of the Federal Rules of Civil Procedure, I hereby submit this interim Report describing the progress achieved to date in implementing the aims of the consent decree and Recommendations of aproposed schedule for future progress.

I. Progress to Date.


A. Progress.



Initially upon appointment, I viewed each site personally and then convened pre-trial conferences in chambers among the parties to become familiar with the legal and technical issues involved in theremediation of the Consent Decree sites. I received oral and written presentations from the parties about the issues. Pre-trial conferences continued to be held on a frequent basis to monitor the progress of theparties' negotiations and of data-gathering and remedial activities.' Where necessary, I assisted the parties as mediator to help resolve disputes and keep cleanup activities moving forward expeditiously. l o date,substantial progress has been made in implementing the aims of the consent decree. As work has gone forward, I visited each site to observe the progress of cleanup activities.

B. Implementation of the Consent Decree.



To date, the following remedial measures have been implemented:

  • In February 1998, CBS removed and properly disposed of 10,000 tons of soil, debris, and sediments from the Interim Storage Facility at the Winston Thomas site. This material consisted of soil and debris from the Anderson Road landfill and sediments from five streambeds that had been previously excavated under the terms of the consent decree.

  • In May 1998, CBS began work on the remediation of the remaining portions of the Winston Thomas site, having previously completed remediation of other components at the site in1997. In 1998, CBS completed remediation of two of the remaining components on the site: the trickling filter and the abandoned lagoons. With respect to the third component, thetertiary lagoon, CBS will have excavated and removed over 85% of the contaminated sludge, including all contaminated clay material that can be removed by dredging by the endof 1998. To date, CBS has removed and properly disposed of 18,000 tons of contaminated sewage sludge and clay soil from the tertiary lagoon, as well as 11,800 tons of contaminated sludge and soil from the abandoned lagoons and 1,100 tons of sediments and rock debris from the trickling filter.
  • As part of the remedial activities at the Winston Thomas site during 1998, the Utilities ServiceBoard of Bloomington, Indiana treated, at its Dillman Road Wastewater Treatment plant, over 29,306,760 gallons of wastewater pumped by CBS from the tertiary lagoon.
  • In September 1998, CBS began work on the excavation of Neal's Dump. CBS has removed200,000 pounds of capacitors and 7,250 tons of contaminated soil and debris. The capacitors were incinerated and the other materials were landfilled. Excavation and site restoration has been completed.

  • The governmental parties provided oversight for the remedial activities implemented by CBS atthe Interim Storage Facility, Winston Thomas, and Neal's Dump during 1998.


In September 1998, the E.P.A. began efforts to implement a spring water treatment system at Illinois Central Springs, located about 2000 feet southeast of the Lemon Lane Landfill. Such a treatment system was not provided for in the original Consent Decree.

In addition to the above remediation work, several significant data gathering events have occurred, including:

  • In March 1998, the E.P.A. and CBS undertook sampling of landfill material at Neal's Landfill.

  • In April 1998, CBS undertook water, sediment, and biota sampling at Conard's
  • In April 1998, CBS began a geologic investigation to locate groundwater conduits around Lemon Lane Landfill. The purpose of the investigation is to obtain data that could be used indeveloping water control or treatment measures. This investigation is continuing.
  • In July 1998, the E.P.A. began a treatability study for treating contaminated groundwater at IllinoisCentral Springs (from Lemon Lane Landfill).

C. Plans.

The parties have engaged in substantial discussions concerning the remediation work to be performed at the remaining three sites: Bennett's Dump, Lemon Lane Landfill, and Neal's Landfill. At a pre-trial conference on November 16, 1998, the parties indicated that they had reached consensus about excavation work to be performed at Bennett'sDump and Lemon Lane Landfill, subject to preparing mutually agreeable Statements of Work andConsent Decree amendments and submission of those documents for formal approval in accordance with the approval processes of each of the parties. The parties further informed me at that time that they had made substantial progress toward consensus on an approach to the excavation of certain materials from Neal's Landfill and consolidation of excavated material from other sites at Neal's Landfill.

D. Outstanding Issues.



Outstanding issues among the parties remain, but can be addressed separately from the current excavation work at the sites. These unresolved issues chiefly concern treatment of water at Lemon LaneLandfill, additional water treatment at Neal's Landfill, removal of sediments from certain streambeds, andthe governments' potential claims for natural resource damages and cost recovery. CBS contends that these claims are barred by the Covenant Not to Sue in the Consent Decree and are not included within the parties' current agreements. The governments contend that the parties agreed or understood that the consideration of water treatment and sediment removal were integral to the targeted excavation scheme planned for Lemon Lane Landfill and Neal's Landfill as an alternative to the now-abandoned complete excavation required in the Consent Decree. The governments want the issues of water treatment and sediment removal to be discussed on the scientific and technical merit of what will protect public health and the environment, otherwise, the extent of the current targeted excavation scheme must be reexamined and possibly reopened if significant public and environmental health risks remain after targeted excavation. CBS agrees to negotiate about additional water treatment and sediment removal and, if consensus is reached, is willing to undertake water treatment and sediment removal beyond the requirements of the Consent Decree, but CBS does not wantto relinquish defenses under the Consent Decree in advance of a consensus and does not want to face the risk of demands for additional excavations after having negotiated and completed expensive targeted excavations.

The parties will continue negotiations about water treatment and sediment removal, natural resource damages, and cost recovery both during and after the excavation work.

II. Proposed Schedule.


In its November 21, 1997 order, the Court stated that it expected that remediation work would be implemented simultaneously at several sites, rather than at one site at a time, and that remediation of the sites would be concluded by the end of 1999. During the course of the pretrial conferences, and through review of materials submitted by the parties and personal visits to the sites themselves, I have become acquainted with the technical and practical problems in undertaking excavation, removal, and water treatment activities at these sites.

At the November 16, 1998 pre-trial conference, the parties collectively proposed a schedule for work to be done at the remaining sites. The parties' proposed schedule would involve work continuing at multiple sites simultaneously, but would call for completion of excavation work by the end of the year 2000, rather than 1999. In addition, the governments propose that negotiations regarding interim and permanent water treatment and sediment removal measures regarding Neal's Landfill and Lemon Lane Landfill/Illinois Central Spring will occur approximately one year after the completion of source control (targeted excavation, etc.) at each site. The interim year will allow (1) CBS to complete its investigation of water conduits at Lemon Lane; (2) the parties to determine whether the need for water treatment/sediment removal has changed; and (3) will allow CBS to determine whether water conduit testing and permanent water treatment/sediment removal is needed at Neal's Landfill.

Under the proposed schedule, CBS would perform the following work in 1999:

  • complete the excavation and closure of the Winston Thomas site, currently anticipated by theend of September 1999;
  • undertake and complete the excavation and closure of the Bennett's Dump site; and
  • undertake and complete the excavation and consolidation of materials at the Neal's Landfillsite, but not construct the cap until the year 2000.

In the year 2000, CBS would perform the following work:

  • construct the cap at Neal's Landfill; and
  • undertake and complete the excavation work, surface water control measures, and capconstruction at Lemon Lane Landfill.



I also propose that the governments' proposal of a schedule for negotiations on water treatment and sediment removal be accepted.

While this proposed schedule would call for work to be completed on the excavation of these sites a year later than contemplated in the order of November 21, 1997, this schedule is both practical and expeditious, considering the work to be performed. Discussions regarding water treatment and sediment removal will occur both while the excavation work is underway and after excavation is completed. Accordingly, I recommend that the Court approve this proposed schedule.

This schedule takes into consideration practical problems affecting the excavation of the two largest sites, Neal's Landfill and Lemon Lane Landfill. Under the proposed schedule, the Neal's Landfill remediation project would take two years; however, it is expected that, during the first year, 1999, all of the material to be excavated would be removed, and material remaining on the site would be consolidated. When this work is done, a landfill footprint would be developed for designing the cap, but the cap would not be installed until the second year, 2000. This would allow CBS to base its cap designon the actual landfill contours following excavation and consolidation, rather than on hypothetical assumptions about the landfill contours made before the excavation and consolidation work is complete. Also, this schedule would allow CBS to construct the cap in warmer rather than colder weather which might affect the integrity of the cap. The end result is expected to be a better designed cap.

With respect to Lemon Lane Landfill, the proposed schedule calls for the commencement of excavation work in the year 2000. The parties have different reasons for wishing to begin work at Lemon Lane Landfill at that time. The E.P.A. is constructing a system to treat groundwater at Illinois Central Springs which is expected to be in operation by the late summer of 1999 and the governmental parties believe that it would be beneficial to have this system operational before the excavation work begins at Lemon Lane Landfill. CBS believes that it is preferable to defer the excavation of the landfill until the year 2000 so that 1999 can be used to design surface water control measures around the landfill that can be implemented at the same time excavation is occurring.

Also, there are practical advantages in not scheduling the excavation work for Lemon Lane Landfill at the same time as excavation work at Neal's Landfill, Bennet's Dump, and Winston Thomas,which are all scheduled for 1999. To perform the excavation work properly at these sites, CBS needs both experienced personnel in-house and experienced contractors; ordinary construction contractors are not qualified for much of this work. CBS would also need to engage substantial transportation resources to move all the excavated material safely from four sites at the same time. If work at all of these sites were going on simultaneously, it would strain CBS's in-house and available contractor resources to a point where the quality of the work could be compromised. CBS believes that staging excavation work at the sites sequentially over a two year period would allow for better overall project management.

III.Recommendations.


I recommend that the Court approve the following schedule:

1. In the year 1999:

   a. complete excavation and closure work at the Winston Thomas site;

   b. undertake and complete excavation and closure at Bennett's Dump; and

   c. undertake and complete excavation and consolidation at Neal's Landfill.

2. In the year 2000, and consistent with the results of the parties' discussions regarding water treatment and sediment removal:

   a. construct a cap at Neal's Landfill; and

   b. excavate and close Lemon Lane Landfill.

3. The parties shall engage in further settlement negotiations regarding water treatment and sediment removal aspects of remediation at Neal's Landfill and Lemon Lane Landfill, including negotiations for permanent water treatment solutions for these sites, approximately one year following the completion of source control activities at each site. Through the year following the completion of source control activities, water conduit and other relevant investigations shall continue and/or be initiated at each site as necessary or useful to determine the need for interim and permanent water treatment at each site and sediment removal.

4. Discussions and negotiations regarding the governments' claims for cost recovery and natural resources damages shall continue.

5. The Court authorizes the Special Master to continue to oversee the implementation of the consent decree and the resolution of disputes among the parties until the work is completed; the Consent Decree, as amended, is fully implemented; and the disputes among the parties are resolved.

Done this 20th day of January, 1999.

Kennard P. FOSTER, Magistrate Judge.


Conferences were held on November 18, 1997; December 10, 1997 (telephone); December11, 1997 (Bloomington); January 7, 1998 (telephone); January 13, 1998; January 22, 1998; March 4,1998 (telephone); March 6, 1998; March 19, 1998 (telephone); March 26, 1998; March 31, 1998(telephone); April 16, 1998 (telephone); June 18, 1998 (telephone); July 14, 1998; August 14, 1998;September 15, 1998; October 16, 1998 (telephone); and November 16, 1998.


 
                               
                               

| The Cast | The Tragedy | The Comedy | The Ending | News | Library | Seating Plan | Top | Home |
                               

CALL (812) 333-8888 FOR MORE INFORMATION OR E-MAIL info@copa.org
                               

The Coaltion Opposed to PCB Ash in Monroe County, Inc. is a nonprofit organization.
205 N. College Ave. - Ste. 713 - P.O. Box 665 - Bloomington, IN 47402-0665 USA
Voice:
+1.812.333.8888 - Fax: +1.812.332.8511 - BBS: +1.812.333.8822

For more info, e-mail info@copa.org. Please send site input to webmaster@copa.org.
Copyright © 1990-98 COPA, Inc. All rights reserved. See legal page for terms
of use and disclaimers. All trademarks belong to their respective owners.
Subscribe to the COPA Mailing List and stay informed on PCBs.