.

COPA page Banner.
                               

CALL (812) 333-8888 FOR MORE INFORMATION OR E-MAIL info@copa.org

                             

Library: Reports: Cleanup: WT

                               
 

CBS Corporation

Bloomington Project
P.O. Box 997
Bloomington, IN 47402
(812) 334-0030
(812) 334-7855 (Fax)

WEEKLY PROJECT STATUS REPORT

WINSTON THOMAS SITE

DATE: July 14, 1998

FROM: Ray Taylor

TO:
 Tom Alcamo, USEPA  John Langley, CBU
 Resa Ramsey, IDEM  Dennis Williamson, Monroe County
 *Bette Conway, CBU  Dottie Alke, CBS
 *Jim Patrick, CBS  Bill Melilli, CBS
 *Mike Hessling, PSARA  Lowell McBurney, BB&L
Todd Scoville, BB&L  *Mark Bertram, Koester
 *Scott Walton, PSARA  
   *(attended meeting)


SUBJECT: Weekly Progress Status Report - July 6 thru July 12

This report is intended to provide a weekly project update regarding the major developments for the remediation work at Winston Thomas. Included are progress updates, sample analytical results, air monitoring results, schedule updates, waste shipping information and field change decisions. Complete sampling logs, shipping logs and air monitoring and meteorological data logs are available at the site.

A project status meeting was held on July 14 to discuss the status of remediation at Winston Thomas. The meeting was attended by CBS, PSARA, Koester, OHM and CBU. The following issues were discussed.

Trickling Filter Project Site Activities - July 6 - July 12

  • Processing of the TF stone was completed on Tuesday July 7. The attached Weekly Status Summary sheet shows that approximately 25,000 tons of stone were processed, total. All the cleaned stone is being stored in drying bed #3.
  • Seventeen (17) roll-offs of debris and sediment, totaling 266 tons were disposed at Southside Landfill last week. A total of 57 roll-offs with 893 ton have been disposed as special waste through Saturday, July 11.
  • A total of 7 rolloffs with 109 ton of small pipe have been shipped to EQ for disposal as TSCA as of Saturday July 11.
  • The conveyors and vibrating screen were decontaminated and disassembled.
  • The results of the trial wipe samples from three sections of large pipe were received. The results ranged from 19 to 22 ug/100 cm2 compared to an allowable level of 100 ug/100 cm2. Based on these results the remainder of the large pipe will be pressure washed and wipe sampled.
  • Approximately 250,000 gallons of accumulated rain water collected in the bottom of the TF was discharged during the past week based on a sample result of 0.6 ug/L PCB.
  • PUF sample results through July 3 have been received. The highest new result is 144 ng/m3. The highest result to date is 207.8 ng/m3 from June 25. The action level for PUF samples is 1000 ng/m3.


Trickling Filter Planned Site Activities - July 13 - July 19

  • Finish shipping small TF pipe to EQ Landfill as TSCA. One rolloff remains.
  • Wash and wipe sample the large pipe headers and concrete slabs in the TF.
  • Scrape the sediment and debris off the bottom of the TF.
  • Wash the walls, floors and trenches of the trickling filter and wipe sample.
  • Send waste debris and sediment to South Side Landfill.
  • Collect, sample and filter wash water for disposal.
  • Finish excavating and sampling the grids around the perimeter of drying bed #1.

Tertiary Lagoon Project Site Activities - July 6 - July 12

  • 35,000 sq. ft. of lagoon surface were dredged from July 7 thru July 13, averaging 5000 sq. ft. per day. A total of 146,000 sq. ft. of the lagoon surface or about 20% of the total lagoon has been dredged to date.
  • Thirty one trucks shipped 746 tons of filter cake to EQ for disposal. 2248 tons of filter cake have been produced and shipped to EQ for disposal to date.
  • Koester increased their work shifts to operate 24 hours a day. Lights have been added to allow dredging during night hours.
  • The 60,000 gallon batch of filtrate water collected and sampled for process verification was discharged on July 7. Koester initiated continuous release of carbon treated water on July 8. A total of 534,930 gallons were discharged last week. Twelve hour grab samples of the discharge water were taken for PCB analysis. The highest result of the week was 0.52 ug/L, compared to the allowable limit of 10.0 ug/L.
  • Koester installed the turbidity meter in the discharge of the water treatment system. A film buildup on the meter sensor is affecting continuous readings of turbidity. Readings with a clean sensor appear to be approximately 0.2 standard units. The on-line turbidity meter is also restricting the flow through the water treatment system. Discussions are being held with CBU to measure turbidity or TSS intermittently on grab samples.
  • Koester received a new conveyor belt to replace the worn belt on the small rental press. It is planned to be installed on the Sunday maintenance day.
  • Exhaust fumes continue to be a problem in the ISF. Koester plans to install exhaust hoods over the diesel exhausts to vent the fumes. Exhaust ducts attached to the diesel exhaust pipes could not withstand the temperature. New washable pre-filters have been installed in the building ventilation system.
  • Water leaking off of the filter presses and mixing with the filtercake in the storage box continues to be a problem. Percent solid samples of filtercake will be taken in the storage box to represent the free water mixed with the filtercake.

Tertiary Lagoon Planned Site Activities - July 13 - July 19

  • Dredge Lagoon
  • Produce 194 tons of filter cake per day over 24 hour shifts.
  • Schedule and transport 8 trucks of filter cake per day to EQ landfill for disposal.
  • Agree with CBU on new method to track turbidity of discharge water. Continue to discharge filtrate to sewer.
  • Replace the worn conveyor belt on the small press.
  • Koester plans to bring in two more carbon vessels to be able to treat water directly from the lagoon to the sewer. Treating only the filtrate from the presses is not lowering the water level in the lagoon fast enough.

Abandoned Lagoon Planned Site Activities - July 13 - July 19

  • OHM mobilized on site on Monday July 13.
  • Water treatment system will be set up.
  • The grid south of the intermittent stream will be excavated and stockpiled.
  • Grids on the west end of the abandoned lagoons will be excavated and stockpiled, to allow a truck road to be built along the drying beds. TF stone will be used to build the road.
  • Other roads to be used on site will be upgraded with TF stone.
  • The intermittent stream will be diverted.

Comments or questions regarding this report should be directed to Jim Patrick on 812-334-0030 or Mike Hessling on 812-335-0424 or Ray Taylor on 412-642-2549.


ATTACHMENTS

There are two attachments this week. * files are in pdf format.

 
                               
                               

| The Cast | The Tragedy | The Comedy | The Ending | News | Library | Seating Plan | Top | Home |
                               

CALL (812) 333-8888 FOR MORE INFORMATION OR E-MAIL info@copa.org
                               

The Coaltion Opposed to PCB Ash in Monroe County, Inc. is a nonprofit organization.
205 N. College Ave. - Ste. 713 - P.O. Box 665 - Bloomington, IN 47402-0665 USA
Voice:
+1.812.333.8888 - Fax: +1.812.332.8511

For more info, e-mail info@copa.org. Please send site input to webmaster@copa.org.
Copyright © 1990-98 COPA, Inc. All rights reserved. See legal page for terms
of use and disclaimers. All trademarks belong to their respective owners.
Subscribe to the COPA Mailing List and stay informed on PCBs.