.

COPA page Banner.
                               

CALL (812) 333-8888 FOR MORE INFORMATION OR E-MAIL info@copa.org

                             

Library: Reports: Cleanup: WT

                               
 

CBS Corporation

Bloomington Project
P.O. Box 997
Bloomington, IN 47402
(812) 334-0030
(812) 334-7855 (Fax)

WEEKLY PROJECT STATUS REPORT

WINSTON THOMAS SITE

DATE: July 7, 1998

FROM: Ray Taylor

TO:
 Tom Alcamo, USEPA  *John Langley, CBU
 Resa Ramsey, IDEM  *Dennis Williamson, Monroe County
 *Bette Conway, CBU  Dottie Alke, CBS
 Ray Taylor, CBS  Bill Melilli, CBS
 *Mike Hessling, PSARA  Lowell McBurney, BB&L
 *Todd Scoville, BB&L  *Mark Bertram, Koester
 *Scott Walton, PSARA  
   *(attended meeting)

SUBJECT: Weekly Progress Status Report - June 29 to July 4

This report is intended to provide a weekly project update regarding the major developments for the remediation work at Winston Thomas. Included are progress updates, sample analytical results, air monitoring results, schedule updates, waste shipping information and field change decisions.

A project status meeting was held on July 7 to discuss the status of remediation at Winston Thomas. The meeting was attended by CBS, PSARA, BB&L, Koester, CBU, and Monroe County. The agendas are attached. The following issues were discussed.

Trickling Filter Project Site Activities - June 29 - July 4

  • BBL estimates that 98% of the TF stone has been processed as of Saturday July 4. The attached Weekly Status Summary sheet shows that 23,551 tons of stone were processed to date. BBL estimates that there will be enough area in drying bed #1 to store all the cleaned stone.
  • About two boxes of debris (dry fines) are being generated for disposal each day. The debris generation rate is still at about 2% of the stone processed.
  • Wet sediment is still filling the phase separation box about every four days in the closed loop process water system.
  • Thirteen(13) roll-offs of debris and sediment, totaling 202.5 tons were disposed at Southside Landfill last week. A total of 40 roll-offs with 627 ton have been disposed as special waste through Saturday, July 4.
  • A total of 6 rolloffs with 95 tons of small pipe have been shipped to EQ for disposal as TSCA as of Saturday July 4.
  • The excavated large pipe was lined up on the bottom of the TF for pressure washing. Three sections of pipe were cleaned and wiped tested. Waiting for results. City has agreed to storage of the large pipe in place in the TF.
  • Process water was changed out with clean water on Sunday, July 5.
  • The City gave approval to discharge the water collected in the bottom of the TF based on a sample result of 0.6 ug/L PCB. The water(approximately 42,000 gallons) was pumped through the 25 micron bag filter to the sanitary sewer, on Tuesday, June 30 and Wednesday July 1.
  • Large(heavy) concrete blocks and slabs around the perimeter of the TF walls and covering the two North to South drainage trenches were discovered by BBL. This material was collected and placed in the North to South central section of the TF for cleaning. BBL estimated there were over 600 blocks and slabs moved and prepared for cleaning. The City of Bloomington agreed that the concrete block and slabs can be left in place after cleaning.
  • Five puff sample results were received. One was at 207.8ng/cm3. Four were below 100ng/cm3.


Trickling Filter Planned Site Activities - July 5 - July 13

  • Balance of TF stone will continue to be processed. Completion targeted for July 8.
  • Continue shipping small TF pipe to EQ Landfill as TSCA. About one and a half rolloffs will be required. One rolloff loaded and ready for shipment.
  • Wash and wipe sample the large pipe headers in the TF after the test lab results, taken to verify the cleaning process, are received ( expected July 7). Cleaning the large pipe is targeted for July 10, 1998.
  • Continue sending waste debris and sediment to South Side Landfill.
  • Demobilization of conveyors and vibrating screen is targeted for July 8 thru July 10, 1998.
  • BBL plans to start cleaning walls and bottom late this week.


Tertiary Lagoon Project Site Activities - June 29 - July 2

  • 27,000sq. ft. of lagoon surface dredged thru July 2. A total of 109,000sq. ft. of the lagoon surface has been dredged to date.
  • Eighteen trucks shipped 420 tons of filter cake produced to EQ for disposal. 1501 tons of filter cake has been produced and shipped to EQ for disposal to date.
  • Koester set up the water treatment system and processed 60,000 gallon of water off the presses. The sample results were BDL for PCBs and within limits for the metals. The City of Bloomington has authorized release of the treated water to the sewer system. Koester is in the process of installing the turbidity meter in the discharge of the water treatment system which will permit continuous release of the treated water from the presses. The City and PSARA will coordinate when the 12 hour samples of the discharge water will be taken so the City can witness.
  • Koester was advised to keep the floor of the truck decon station clean after each truck is deconed to eliminate the possibility of the following trucks tracking sludge particles from the area to the outside of the Interim Storage Facility.
  • Koester has had to splice the conveyor belt on the small press on several occasions affecting the production rate of the filter cake. Koester is expecting the supplier of the press to ship a new conveyor belt and replace the worn belt.


Tertiary Lagoon Planned Site Activities - July 6 - July 13

  • Dredge Lagoon
  • Produce 160 tons of filter cake per day over 20 hour shifts.
  • Schedule and transport 7 trucks of filter cake per day to EQ landfill for disposal.
  • Release the 60,000 gallons of treated water from the presses to the sewer.
  • Replace the worn conveyor belt on the small press.

Air quality in the ISF continues to be a problem due to the number of diesel engines operating in the building. Koester will continue to work to vent all diesel engines except the trucks and loader outside the building. To improve the flowrate of the air handling system, the air filters are being almost daily, and the third stage filters have been removed.

Comments or questions regarding this report should be directed to Jim Patrick on 812-334-0030 or Mike Hessling on 812-335-0424.


ATTACHMENTS

There are four attachments this week. * files are in pdf format.

 
                               
                               

| The Cast | The Tragedy | The Comedy | The Ending | News | Library | Seating Plan | Top | Home |
                               

CALL (812) 333-8888 FOR MORE INFORMATION OR E-MAIL info@copa.org
                               

The Coaltion Opposed to PCB Ash in Monroe County, Inc. is a nonprofit organization.
205 N. College Ave. - Ste. 713 - P.O. Box 665 - Bloomington, IN 47402-0665 USA
Voice:
+1.812.333.8888 - Fax: +1.812.332.8511

For more info, e-mail info@copa.org. Please send site input to webmaster@copa.org.
Copyright © 1990-98 COPA, Inc. All rights reserved. See legal page for terms
of use and disclaimers. All trademarks belong to their respective owners.
Subscribe to the COPA Mailing List and stay informed on PCBs.