|
|
CBS Corporation
Bloomington Project
P.O. Box 997
Bloomington, IN 47402
(812) 334-0030
(812) 334-7855 (Fax)
WEEKLY PROJECT STATUS REPORT
WINSTON THOMAS SITE
DATE: June 17, 1998
FROM: Ray Taylor
TO:
|
Tom Alcamo, USEPA |
*John Langley, CBU |
|
Resa Ramsey, IDEM |
*Dennis Williamson, Monroe County |
|
*Bette Conway, CBU |
Dottie Alke, CBS |
|
*Jim Patrick, CBS |
Bill Melilli, CBS |
|
*Mike Hessling, PSARA |
Lowell McBurney, BB&L |
|
*Todd Scoville, BB&L |
*Mark Bertram, Koester |
|
|
|
|
|
*(attended meeting) |
SUBJECT: Weekly Progress Status Report - June 9 to
June 16
This report is intended to provide a weekly project update
regarding the major developments for the remediation work at
Winston Thomas. Included are progress updates, sample analytical
results, air monitoring results, schedule updates, waste shipping
information and field change decisions.
A project status meeting was held on June 16 to discuss the
status of remediation at Winston Thomas. The meeting was attended
by CBS, PSARA, BB&L, Koester, CBU and Monroe County. The
agendas are attached. The following issues were discussed.
Site Activities - June 9 to June 16
Trickling Filter (TF) Project
- BB&L estimates that 30% of the TF stone has been processed,
to date. The estimated processing rate of 200 ton / hour may
be somewhat high. Based on an estimate of 27,000 ton of stone
total, the processing rate would be around 150 ton / hour. The
attached Weekly Status Summary sheet shows that 5,025 ton of
stone was processed this week, at 150 ton/hr.
- Wipe sample results for the cleaned TF rock (treated rock)
are shown in the attached sample log. The wipe sample results
for the first nine days showed an upward trend to 7.8 ug/100
cm2. Per the work plan, adjustments were made to the process
before the results exceeded 10ug/ 100 CM2 . The closed loop wash
water was changed out. The PCB content of the wash water had
increased from 0.24 to 2.4 ug/L from June 5 to June 9 as shown
in the attached sample log. The bag filters used in the closed
loop water system were changed from 100 mesh to 5 micron to keep
the water cleaner. The water spray rate was also increased. These
changes resulted in the daily wipe sample results dropping from
an average of 7.8 ug/ 100 cm2 on Saturday, June 13 to 3.4 and
2.4 ug/100 cm2 on Monday and Tuesday, respectively, after the
process water was changed out. Wipe samples will continue to
be taken daily until the results stabilize.
- Some tile fragments from the cleaned stone discharge were
wipe sampled as part of the five daily production samples. Results
are shown in the attached sample log. Tile sample results are
typical of the stone results.
- About one box of debris (dry fines) is being generated for
disposal each day. A box contains about 15 to 18 ton, or about
2% of the stone processed.
- The RCRA characterization of the debris was received from
Heritage showing the material to be non-RCRA. The PCB analysis
from each of the first five boxes is shown on the attached sample
log, showing the debris to be non-TSCA.
- PCB analysis on the debris will be scaled back to sample
every fourth box. Four boxes hold less than 60 cubic yards of
debris. The work plan calls for sampling 60 cubic yard stockpiles.
- Wet sediment is filling the phase separation box about every
4 or 5 days in the closed loop process water system. Two boxes
are being rotated to the South Side landfill as they fill.
- Nine rolloffs of debris, totaling 147 ton and one roll-off
of sediment weighing 17 ton have been disposed at Southside Landfill
as special waste, to date.
- The rain water collected in the TF was analyzed at 0.6 ug/L.
Results on the metals required per the CBU discharge permit are
pending. If permit levels are satisfied the TF water will again
be pumped through a bag filter to remove suspended solids, directly
to the sanitary sewer.
- Due to the cost of roll-off disposal for the large pipe headers
in the TF, it was decided to wash and sample the 600 feet of
large pipe. Small pipe is being sized and loaded into Wills roll-offs
for disposal at EQ as TSCA.
- BB&L increased their work shift from 10 to 12 hours per
day starting Monday, June 15.
Tertiary Lagoon Project
- The harvesting of vegetation from the tertiary lagoon (TL)
was completed Saturday, June 13.
- Assembly of the process system inside the ISF, except for
the new press was completed.
- The dredge pipeline from the TL to the ISF was completed
and pressure tested.
- The guide lines were anchored on the south end of the TL
to guide the dredge.
- The first drop of filter cake was produced on Thursday, June
11. Cycle times have been around one hour per cycle using the
centrifugal pumps to fill the filter presses with sludge. On
Saturday and Monday 12 cycles were run on both presses in a 12
hour shift.
- Percent solids of the filter cake have varied from 37 to
52%. Specific gravity of the cake is between 1.2 and 1.3.
- The first trucks of filter cake were sent to EQ landfill
on Monday, June 15. Eight trucks containing 192 ton of filter
cake were sent Monday and four trucks with 96 tons were shipped
on Tuesday. The material was accepted by the landfill without
any problems.
- The new, third press and its filter clothes arrived on Saturday,
6/13 but did not include the platform and conveyor. These remaining
components will be received on Thursday, 6/18. Koester anticipates
the third press will be installed over the weekend and operational
by Monday, 6/22.
- The filter press process was upset on Tuesday because of
very watery sludge being pumped by the dredge. The sludge with
very little solids caused the filter cloth to blind off and produced
thin cakes. The watery sludge from the holding frac tanks was
returned to the lagoon and thicker sludge was pumped by the dredge.
- To allow better dredging control, Koester decided to drop
the level of the water in the lagoon more than a foot to expose
the top of the sludge. To lower the lagoon level, filtrate water
will be treated and discharged to the sewer per the CBU discharge
permit.
- The approved water discharge permit was received from the
CBU Utilities Board this week.
Drying Bed Perimeter
- No further excavation was performed due to wet weather. The
northern perimeter of DB #1 will be excavated as TSCA when time
and weather permits.
Abandoned Lagoon
- Analytical results of the geoprobe sampling in the Abandoned
Lagoon were received from Heritage Labs. PSARA presented these
results to CBS this week.
Digesters
- The three digesters were resampled on Wednesday, June 10
by PSARA. One location in each of digesters #1, 3 and 4 corresponding
to earlier Earth Tech sampling were re-sampled per agreement
with the Consent Decree parties.
- Sample results obtained in digester #1 and #3 were 26 and
1.3 ug/cm2, respectively. No visible staining was observed in
these locations.
- The sample location for digester #4 was within a visibly
discolored area. The sample result was 130 ug/cm2. The attached
PSARA figure shows the sample locations and results. It also
shows the location of the discolored area in digester #4. This
area will be power washed when the washer is brought in to wash
the large diameter Trickling Filter pipe.
Health and Safety
- Additional air monitoring results were obtained through June
8, as shown on the attached Air Sampling Log. These samples were
taken during the trickling filter stone excavation and processing.
The highest new result is 25.9 ng/m3 , which is the highest level
to date. The allowable level is 1000 ng/M3.
- Meteorological data collected to select the appropriate air
monitoring sample for analysis is shown in the attached Weekly
Meteorological Data Report.
- Additional personnel sampling was performed in the TF area.
The attached Personnel Sampling Log shows that all results obtained
so far are non-detect.
- The City Utilities Service Board approved the water discharge
permit as described in last week's report.
- The sump pumps on the trickling filter process equipment
pads have been able to keep up with the heavy rains being experienced.
Planned Activities for the Week of June 17 - 23
Trickling Filter
- Continue processing TF stone at 150 ton/hr.
- Ship small TF pipe to EQ Landfill as TSCA.
- Plan to wash out and wipe sample large TF pipe instead of
sending for TSCA disposal.
- Continue sending waste debris and sediment to South Side
Landfill.
- Use 25 micron bags in the process water bag filters instead
of 5 micron to reduce the amount of bag washing required.
- Pump collected rain water from the Trickling Filter to the
sewer after receiving sample results for PCB and other permit
requirements.
Tertiary Lagoon
- Receive the platform and conveyor for the new, third press
and install and check out the press over the weekend. All three
presses should be operational by Monday, 6/22.
- The water treatment system is planned to be installed in
the ISF this weekend. The water treatment process will be confirmed
per the CBU discharge permit by treating, sampling and holding
the first 60,000 gallon batch. Analytical results will be obtained
for the permit requirements before the first batch is discharged.
- Per the CBU discharge permit, after the treatment process
is verified, filtrate from the presses will be treated through
carbon and directly discharged to the sewer at approximately
350 gpm. The effluent will be monitored continuously for turbidity
and sampled every 12 hours and analyzed for PCB, per the discharge
permit.
- Koester will provide a revised schedule once the total system
is in operation and processing rates are determined.
- Koester has delayed the start of second shift operation until
the third press becomes operational.
- Scaffolding will be set up outside the ISF near the scale
to allow access for lining and tarping trucks.
- The dredging progress across the lagoon will be mapped.
Digesters
- Schedule when the discolored area in digester #4 will be
pressure washed and resampled.
Abandoned Lagoon
- The geoprobe sampling data and a new excavation map based
on the sampling should be available.
Comments or questions regarding this report should be directed
to Jim Patrick on 812-334-0030 or Mike Hessling on 812-335-0424
or Ray Taylor on 812-335-8780.
ATTACHMENTS
There are fourteen attachments this week. * files are in pdf
format.
- * Weekly Project Status Report - Trickling
Filter Project
- Trickling Filter Weekly Meeting
Agenda - June 16, 1998
- Tertiary Lagoon Weekly Meeting
Agenda - June 16, 1998
- * Sample Log - Trickling Filter Rock,
page 1 of 4
- * Sample Log - Trickling Filter Rock,
page 2 of 4
- * Sample Log - Trickling Filter Rock,
page 3 of 4
- * Sample Log - Trickling Filter Rock,
page 4 of 4
- * Sample Log - Debris, Sediment, and
Miscellaneous Sampling
- * Sample Log - Trickling Filter Water
Samples
- * Air Sampling Log, page 1 of
2
- * Air Sampling Log, page 2 of
2
- * Weekly Meteorological Data Report
- * Personnel Sampling Log
- * Sample Locations & Area for Recleaning
in Digesters
|
|