|
|
CBS Corporation
Bloomington Project
P.O. Box 997
Bloomington, IN 47402
(812) 334-0030
(812) 334-7855 (Fax)
WEEKLY PROJECT STATUS REPORT
WINSTON THOMAS SITE
DATE: June 10, 1998
FROM: Ray Taylor
TO:
|
Tom Alcamo, USEPA |
John Langley, CBU |
|
Resa Ramsey, IDEM |
*Dennis Williamson, Monroe County |
|
*Bette Conway, CBU |
Dottie Alke, CBS |
|
*Jim Patrick, CBS |
Bill Melilli, CBS |
|
*Mike Hessling, PSARA |
Lowell McBurney, BB&L |
|
*Todd Scoville, BB&L |
*Mark Bertram, Koester |
|
|
|
|
|
*(attended meeting) |
SUBJECT: Weekly Progress Status Report - June 2 to June 9
This report is intended to provide a weekly project update
regarding the major developments for the remediation work at
Winston Thomas. Included are progress updates, sample analytical
results, air monitoring results, schedule updates, waste shipping
information and field change decisions.
A project status meeting was held on June 9 to discuss the
status of remediation at Winston Thomas. The meeting was attended
by CBS, PSARA, BB&L, Koester, CBU and Monroe County. The
agendas are attached. The following issues were discussed.
Site Activities - June 2 to June 9
Trickling Filter Project
- The three demonstration trial runs were completed on the
screening / washing system to clean the Trickling Filter (TF)
rock. Processing rates of 100, 150 and 200 ton/hr were run. The
last two tests were performed with the downstream spray bar turned
off to prevent water carry over with the clean stone. All wipe
sample results on the washed stone were non-detect (<1 ug/
100 cm2) for all the test runs as shown in the attached Sample
Log. A memo was issued to the consent decree parties describing
the test runs and notifying the parties that BB&L will process
the TF rock at the 200 ton/hr rate with the downstream spray
bar off.
-
- Cleaned TF rock wipe sample results for the trial (compliance)
tests and the first four days of production are shown in the
attached table. Per the approved sampling plan, if the daily
sample results are below 10 ug/100 cm2 for seven consecutive
days of operation and if no obvious upward trends have been identified,
the daily sampling of the stone will be discontinued.
- Samples of the debris (fines) collected off of the stone
during all the trial runs were composited per the approved sampling
plan and sent to Heritage for analysis of PCB and RCRA characterization
for disposal. The PCB result was 1.9 ppm indicating the debris
can be disposed as non-TSCA to the South Side Landfill. Disposal
will be after receipt of the RCRA characterization, which is
due by the end of the week.
- PCB analysis for the debris in each roll off box of debris
generated is shown in the attached table. If the results continue
to be consistently low after sampling six roll offs of debris,
CBS will consider the process debris to be sufficiently characterized
for Special Waste disposal. No additional PCB sampling will be
performed on the debris sent to the South Side Landfill.
- The carryover of process water with the clean stone was eliminated
by shutting off the downstream spray bar before the trial test
runs at 150 and 200 ton/hr. Because the carryover water was eliminated,
the need for the sump in the clean stone discharge area was eliminated.
- A new quarter inch harp screen was installed to replace the
screen with broken strands.
- The attached status report summary sheet shows that approximately
3600 ton of TF stone was processed from June I to 6. Approximately
50 ton of debris (fines) were generated for a waste generation
rate of less than 2%.
- The sediment collection rate in the process water collection
frac tank will fill the tank in about I 1/2 weeks. The tank will
then be changed out and the full box allowed to sit to drain
completely. Dry fines from the debris collection box may be added
to assure free water will not shake out while the sediment is
shipped to the landfill. The sediment was sampled and analyzed
at 1.8 ppm. Based on this result the sediment will be disposed
as non-TSCA to South Side Landfill.
- The bag filters in the process water loop have been arranged
in parallel, with 100 mesh bags in both. The bag screens are
being replaced each day and washed out for reuse the next day.
- The clay tiles in the bottom of the TF were found to be broken
apart. The tile segments are being excavated and processed with
the stone. It was agreed at the weekly meeting to grab some tile
fragments from the cleaned stone discharge to be wipe sampled
as part of the five daily production samples.
- The recirculated process water spray rate is estimated between
50 and 100 gpm. A sample of the process water was collected on
6/5 after two days of processing and the three compliance tests.
The PCB concentration was analyzed at 0.24 ug/L. The closed loop
recirculated water will be sampled every three days to track
any PCB increase. The disposal of the closed loop water will
be performed per the attached BBL memo, satisfying all CBU water
discharge requirements per the pending Water Discharge Permit.
- Approximately 30,000 gallons of rain water has again collected
in the TF. John Langley gave his approval to sample the water
collected in the TF as a batch per the draft CBU discharge permit.
If permit levels are satisfied the TF water will again be pumped
directly to the sanitary sewer.
- The large pipe headers in the TF consist of two runs about
200 feet long of 32 inch pipe tapering down to about 12 inch
pipe. The headers were found to contain residual sludge like
the smaller pipe. It was decided to size and dispose of this
pipe as TSCA along with the smaller pipe.
- Since the waste debris (fines) generated from the process
has been characterized as nonTSCA it is being disposed of in
a local Special Waste Landfill, South Side Landfill. It was decided
to have South Side Landfill's broker, Terra Limited, provide
local roll off service for the debris instead having Koester
provide roll offs from Wills Trucking. Wills was bringing rolloffs
in from Ohio for the local haul to Indianapolis. BB&L and
PSARA will coordinate transportation of the debris and water
system sediment to South Side Landfill. Koester will still provide
rolloffs from Wills to transport the TF pipe to EQ landfill in
Michigan.
Tertiary Lagoon Project
- The harvesting of vegetation from the tertiary lagoon (TF)
continued through the week. The harvester will remain on site
and be operated by Koester as needed.
- The 48 ft x 48 ft steel filtercake storage box was fabricated.
- Work was nearly completed on welding the dredge pipeline
from the TL to the ISF.
- The decon trailer was installed.
- The 110 cu. ft rental press which arrived from Louisiana
on Wednesday 6/3 contained damaged membrane plates. All the plates
were replaced with new. A memo was received from Koester explaining
the delay from the damaged plates. The filter cloth for the rental
press arrived Monday, 6/8. Filter cloth for the 220 cu ft press
arrived Tuesday 6/9.
- Assembly of the process system inside the ISF, except for
the new press was nearly complete by Tuesday, 6/9.
- Polymer was mixed and allowed to age before use.
- Diesel powered centrifugal pumps were added to supplement
the diaphragm pumps to fill the filter presses with sludge. The
centrifugal pumps will be connected in parallel with the diaphragm
pumps and used to initially fill the presses. The diaphragm pumps
will be used to finish pressurizing the cake. It is anticipated
that the centrifugal pumps will increase the cycle rate to speed
up processing. The centrifugal pumps will be checked out to assure
they do not cause sludge "blow by" through the filter
cloth.
- Pilot testing of polymers was completed. The polymer selected
during the previous pilot tests, Allied Colloids #778, is still
considered the best polymer to use. This polymer was shown to
work with pure sludge, pure clay or mixtures of sludge and clay.
- A meeting was held with John Teague and Bob Koss of EQ Landfill
and Koester to coordinate TSCA transportation. EQ has agreed
to extend the daily receiving hours until 8 pm, starting in mid-June.
EQ also indicated they would receive a minimum of 10 to 15 trucks
on Saturday mornings at no extra charge.
Dry Bed Perimeter
- No further excavation was performed due to TF startup and
wet weather. The northern perimeter of DB #1 will be excavated
as TSCA when time and weather permit.
Abandoned Lagoon
- Analytical results of the geoprobe sampling in the Abandoned
Lagoon were received from Heritage Labs. PSARA will present these
results to CBS this week.
- Pre-excavation elevations were surveyed for all grids in
the Abandoned Lagoon.
Digesters
- The three digesters were not resampled due to weather.
- Stone was backfilled around the digesters to fill the previously
excavated grids.
Health and Safety
- Additional air monitoring results were obtained through June
2, as shown on the attached Air Sampling Log. These samples were
taken during the trickling filter stone excavation and processing.
The highest new result is 13.1 ng/m3. The highest result to date
is 22 ng/m3, compared to an allowable level of 1000 ng/m3.
- Meteorological data collected to select the appropriate air
monitoring sample for analysis is shown in the attached Weekly
Meteorological Data Report.
- Personnel sampling was initiated in the TF area. The attached
Personnel Sampling Log shows that all results obtained so far
are non-detect.
- The need for the sump in the clean TF stone discharge area
was eliminated since the carryover water was eliminated by shutting
off the downstream spray bar.
- No water was discharged to CBU this week.
- It was decided that CBS, PSARA and CBU will identify and
map stormwater outfalls to Clear Creek from the Winston Thomas
site. Outfalls will be observed for flow during storm conditions
and samples of sediment and water may be taken by the City. CBU
will clear paths to known outfalls.
- It was agreed that BBL will install barriers to prevent personnel
access under the conveyors.
- PSARA requested that Koester provide a copy of the operating
manual for the harvester.
- John Langley reported on the City Utilities Service Board's
review of the draft Water Discharge Permit. Water from the Trickling
Filter processing can be batched, sampled and discharged after
confirmation is received that analysis meets the permit levels.
No treatment (i.e. carbon) will be required if the water meets
discharge requirements.
- Water from the Tertiary Lagoon processing will be treated
through a filter press lined with diatomaceous earth and then
through carbon. An initial batch of 60,000 gallons will be held,
sampled and confirmed to meet permit requirements before it is
discharged, to confirm that the treatment process is adequate.
After the treatment system is confirmed, water can be directly
discharged after treatment without holding for confirmation.
Grab samples of the treated water are to be taken every 12 hours
and analyzed to confirm permit limits are being met. Analytical
results will be required within 24 hours of sampling. A turbidity
meter will be required on the treated water discharge with a
chart recorder. A turbidity limit of 5 standard units was established
by the City.
- During storm events when the POTW approaches full capacity,
CBU will notify CBS to shut down any discharge of process water
until further notice.
Planned Activities for the Week of June 10 - 16
Trickling Filter
- Obtain RCRA characterization analysis of debris for disposal
waste profile.
- Continue processing TF stone at 200 ton/hr.
- Dispose of small TF pipe as TSCA.
- Start stockpiling and sizing large TF pipe for TSCA disposal.
- Install sump pump on upper equipment pad to pump stormwater
to process water tank.
- Once RCRA characterization is received, start sending waste
debris to South Side Landfill.
Tertiary Lagoon
- Continue weed harvesting
- Complete equipment setup and check out in the ISF.
- Complete installation of the dredge guide wires and pipeline.
Pressure test pipeline.
- Set up secondary containnent around the shaker box which
receives the sludge from the
- dredge.
- Start up the system initially only on the smaller 110 cu
ft press to confirm process parameters and to check the quality
of the filtercake produced.
- The new, third press and its filter clothes are scheduled
to arrive on Saturday, 6/13 and be
- installed over the weekend. Koester anticipates that all
three presses should be operational
- by Monday, 6/15.
- Initiate full scale dredging and dewatering operation.
- CBU plans to mow the grass on the TL berms.
- Koester will provide a revised schedule once the system is
in operation and processing rates are determined.
- Koester plans to process 24 hours a day, seven days a week
until July 3. They will shut down for the holiday from July 3
until July 6.
Digesters
- Resample three digesters to compare with EPA samples.
Abandoned Lagoon
- Prepare revised excavation drawing based on new sampling
results.
Comments or questions regarding this report should be directed
to Jim Patrick on 812-334-0030 or Mike Hessling on 812-335-0424
or Ray Taylor on 812-335-8780.
ATTACHMENTS
There are eleven attachments this week. * files are in pdf
format.
|
|