|
|
CBS Corporation
Bloomington Project
P.O. Box 997
Bloomington, IN 47402
(812) 334-0030
(812) 334-7855 (Fax)
WEEKLY PROJECT STATUS REPORT
WINSTON THOMAS SITE
DATE: June 3, 1998
FROM: Ray Taylor
TO:
|
Tom Alcamo, USEPA |
John Langley, CBU |
|
Resa Ramsey, IDEM |
*Dennis Williamson, Monroe County |
|
*Bette Conway, CBU |
Dottie Alke, CBS |
|
*Jim Patrick, CBS |
Bill Melilli, CBS |
|
*Mike Hessling, PSARA |
*Lowell McBurney, BB&L |
|
*Todd Scoville, BB&L |
*Mark Bertram, Koester |
|
|
|
|
|
*(attended meeting) |
SUBJECT: Weekly Progress Status Report - May 26 - June 2
This report is intended to provide a weekly project update
regarding the major developments for the remediation work at
Winston Thomas. Included are progress updates, sample analytical
results, air monitoring results, schedule updates, waste shipping
information and field change decisions.
A project status meeting was held on June 2 to discuss the
status of remediation. at Winston Thomas. The meeting was attended
by CBS, PSARA, BB&L, CBU and Monroe County. The agendas are
attached. The following issues were discussed.
Site Activities - May 26 to June 2
Trickling Filter Project
- Water in the trickling filter (TF) was sampled and analyzed
for PCB. The results obtained were 0.39 and 0.18 ug/L. The results
were provided to John Langley of CBU, who gave approval to discharge
the water to the sanitary sewer. The water was discharged on
Friday, 5/29.
- The pipe stockpile in the TF was sampled. Six wipe samples
of the pipe surface and two composite samples of the material
inside the pipe were obtained and analyzed for PCB. Wipe sample
results ranged from 5.5 to 28 ug/ 100cm 2 . The composite samples
of material inside the pipe were 78 and 170 ppm. Based on these
results the pipe will be disposed of as TSCA to EQ landfill in
rolloffs provided by Koester.
- The conveyors, vibrating screens and spray wash equipment
setup was completed. On Monday, 6/1, the first process test run
was conducted. The conveyors were set at the low speed to process
about 100 ton/hr. The water spray was set at 40% of full capacity.
The amount of waste generated from the stone was about 1% of
the stone processed. Four wipe samples of the processed stone
was taken and wipe sampled for PCB. Results of all four samples
were non-detect, ( < 1 ug/100cm 2).
- Based on the results of the first test run, modifications
were made to the equipment to contain stone on the conveyor,
contain dust and minimize water carry over with the clean stone.
- BB&L requested a field change to the work plan to convey
the waste and debris removed from the TF stone directly into
roll-offs for disposal. This allows for better containment of
dust and eliminates any spillage that could occur in handling
the waste from open piles into dump trailers. This field change
is described in the attached memorandum, Field Change No. 3 -
Waste Piles.
- A composite sample from the debris roll-off will be analyzed
to characterize the waste for non-TSCA disposal. If the debris
is to be disposed as TSCA, no additional PCB sampling will be
required. A sample of the debris from the trial runs will be
analyzed for RCRA parameters, including TCLP, reactivity, corrosivity,
and ignitability to generate a waste profile for disposal.
- Work hours for BB&L will be 7 to 5:30, Monday through
Saturday.
Tertiary Lagoon Project
- The harvester started removing vegetation from lagoon on
Monday, 6/1. The harvested vegetation will be laid out on the
bank next to the ISF, on plastic, to drain and dry. Once the
vegetation has dried, it will be sampled and characterized for
disposal.
- The shipment of the press, mix tank and shaker screen from
Louisiana was delayed due to permit problems in Tennessee. The
shipment arrived on site Wednesday, 6/3. Assembly of the process
system inside the ISF was delayed until the shaker screen and
mix tank was delivered and placed inside the ISF. The first press
and the rest of the equipment is on site.
- Koester anticipates to start the dredging and pressing operation
by the end of the week, Saturday, June 6.
- The new, third press is still scheduled to be delivered by
the manufacturer on June 12.
- Operation will begin with only two presses at a reduced rate
until the third unit is assembled and placed on line.
- Additional pilot press testing on the sludge began on Monday,
6/1. Different polymers are being investigated to optimize dewatering.
- The water level in the lagoon has been adjusted down to an
elevation of about 682.3 feet. Koester requested that the level
be left there for the dredging operation.
- Attached is a revised schedule from Koester.
Dry Bed Perimeter
- Delineation sampling of Drying Bed (DB) #1 was completed.
The entire length of the nor-them perimeter of DB #1 will be
excavated as TSCA when time permits. The enclosed map shows the
status of DB #1.
Abandoned Lagoon
- Sampling of the shallow grids in the Abandoned Lagoon (AL)
was completed on Wednesday, 5/27. Results of this sampling will
be available in about two weeks.
- Geoprobe sampling to depth was completed in the Abandon Lagoon
and on the south berm of the Tertiary Lagoon on Tuesday, 6/3.
Results from the geoprobe sampling will be available in about
two weeks.
Health and Safety
- Air monitoring results were obtained for May 19 and 21, taken
during the drying bed perimeter excavation and the trickling
filter pipe removal. Results were 6 and 22 ng/m3, respectively
as shown in the attached table.
- Sumps and sump pumps were set up in the Trickling filter
area for storm water management to isolate and contain storm
water on the exclusion zone pad and to prevent clean storrn water
from pooling onto the exclusion zone.
- A plastic lined sump was established in the clean TF stone
discharge area to contain water that carries over with the stone.
This water will be pumped back to the process water frac tank
if it accumulates.
Planned Activities for the Week of June 3 - 9
Trickling Filter
- Complete process testing at 150 and 200 ton per hour.
- Obtain wipe samples of processed stone to confirm process.
- Obtain RCRA characterization analysis of debris for disposal
waste profile.
- Process TF stone at highest processing rate found to be acceptable.
- Initiate personnel monitoring.
- Dispose of TF pipe as TSCA.
Tertiary Lagoon
- Complete weed harvesting
- Complete equipment setup
- Complete pilot scale press tests to select a polymer to optimize
dewatering.
- Initiate full scale dredging and dewatering operation.
- Meet with EQ on Wednesday 6/3 to coordinate TSCA transportation
and disposal.
Digesters
- Resample three digesters to compare with EPA samples.
- Backfill around digesters with clean stone.
Abandoned Lagoon
- Survey pre-excavation elevations.
- Prepare revised excavation drawing based on new sampling
results.
Comments or questions regarding this report should be directed
to Jim Patrick on 812-334-0030 or Mike Hessling on 812-335-0424
or Ray Taylor on 812-335-8780.
Attachments
* Weekly Project Status
Report - May 26 to June 2, 1998
Trickling Filter Weekly Meeting
Agenda - June 2, 1998
Tertiary Lagoon Weekly Meeting
Agenda - June 2, 1998
* Field Change Number 3
* Work Schedule Timeline,
page 1 of 2. Revised June 4, 1998
* Work Schedule Timeline, page 2
of 2. Revised June 4, 1998
* Drying Bed #1 - Sampling Results
and Excavtion Areas as of June 2, 1998
* Air Sampling Log - From May 19
to May 31, 1998
* Weekly Metrological Data Report
- Week ending May 31, 1998
Note: Files with * are in pdf format. |
|