Citizens Information Committee
Summary of Public Meeting
February 8, 1999
Bloomington, Indiana
Summary of Points presented by Tom Alcomo, USEPA
Winston-Thomas
Comments Submitted to CBS on Final Report(s) for the Sludge
Digesters, Sludge Drying Beds, Abandoned Lagoons and Trickling
Filter
Sampling Completed on the Southern Berm of Tertiary Lagoon
Contamination within Southern Berm
Tertiary Lagoon Remediation may be Initiated - Weather Dependent
EPA Developing Drawing with Historical and Verification Sampling
Plans for Reuse of Property by City of Bloomington
Bennett's Dump
Work Scheduled to Begin in Mid-June
Magnetometer Study Completed
Beginning Negotiations on Remediation Statement of Work
Areas Outside Fence Lines will be Investigated
Neal's Dump
Photos
of Neal's Dump
Submitted Comments to CBS on Final Report
Once Approved - Administrative Record will be Updated
Reviewing Groundwater Monitoring Plan
Delist Neal's Dump from NPL
Lemon Lane Landfill
Conduit Study Continues with 13 New Wells and Dye Tracing
Dioxin Sampling Outside Fence Line
Griffin Property to be Fenced Until Remediation in Spring/Summer
Proposed Plan for Source Control in Spring
Illinois Central Springs
Design 50% Completed
Construction Begins in April 1999
Treatability Study for Low Flow Completed
|