4.4.6.6 Implementability -- Alternative 6 Implementation considerations for bioremediation systems include technical feasibility, administrative feasibility, and availability of services and materials. Additional information is also needed to implement bioremediation systems. These considerations are discussed below. Technical Feasibility Several technical difficulties may be encountered during implementation of this alternative. Under both Scenarios 1 and 2, the proposed location for the CTF does not provide adequate area for the required number of CSPB cells and support equipment. Depending on the required size of the CSPB cells and the permeability of the materials being treated, the air distribution system may require extensive piping to provide adequate aeration to all of the material in the cells. If tilling or other mechanical mixing equipment is used to aerate the soils, the piping system would not be needed, but soil cannot be placed in lifts deeper than the mixing equipment can reach. During anaerobic treatment, application of amendment solutions may require either temporary removal of the synthetic liner, or, if the cover is to remain in place, installation of the distribution system at or below the surface of the contaminated materials in the CSPB cells. Administrative Feasibility For this alternative, federal, state, and local approval would be required. Monitoring considerations include the need to develop a sampling scheme to collect representative samples that accurately characterize the PCB levels remaining in contaminated materials during treatment. During the anaerobic phase of treatment, the levels of individual congeners should be analyzed to determine the extent of dechlorination and when to begin aerobic treatment. During aerobic treatment, total PCB concentrations should be analyzed to determine if the cleanup standard has been achieved. This alternative poses a low risk of exposure to releases to the environment from system failure. The CSPB cells should be provided with adequate controls, including an impermeable bottom liner and leachate collection system, to prevent releases of contaminated leachate. During in situ biological treatment, contaminants could potentially leach from lagoon sludges into groundwater. Availability of Services and Materials Most equipment necessary to implement this alternative is readily available, particularly for CSPB. At some PCB-contaminated sites, in situ biological treatment field studies involved more specialized equipment, including steel caisson reactors used as testing cells at the Hudson River site (Harkness 1993), and dredge-mounted pumps to shear lagoon sludges and pressurized pipeline contractors to inject oxygen gas used at the French Limited Superfund site (DEVO 1992). Because of the amount of research that has been conducted on bioremediation at the General Electric Company Hudson River sites, the French Limited Superfund Site, and other sites, specialists in PCB bioremediation are available; however, few specialists have experience beyond the laboratory scale. Some vendors of biological treatment technologies offer proprietary mixtures of amendments, nutrients, and bacterial strains. However, the widespread occurrence of anaerobic dechlorination suggests that either dechlorinating organisms are ubiquitous or that the dechlorination process is part of a biochemical pathway common to many different anaerobic organisms (Abramowicz and others 1993). Treatability studies should therefore be conducted to determine how to stimulate growth in indigenous microorganisms using common limiting nutrients and known PCB-analog amendment stimulants before testing nonindigenous strains or unknown proprietary mixtures. Although vendors with demonstrated experience in biological treatment of PCBs beyond the laboratory and pilot scale are not available, some vendors have demonstrated experience in treating other contaminants through biological treatment. After optimal conditions for biological treatment of wastes from the CD sites are determined during laboratory- and pilot-scale studies, experienced vendors are available to design full-scale systems. Additional Information Needed to Implement Bioremediation Additional information is needed before this alternative can be implemented. First, an updated characterization of the contaminated materials at the Bennett Stone Quarry, Lemon Lane Landfill, Neal's Dump, and Neal's Landfill sites and at the ISF is needed to determine the degree of chlorination of the PCB congeners present at these sites and the presence and concentration of other RCRA Appendix IX contaminants. Analytical information indicates that the PCBs originally disposed of at the sites primarily consisted of Aroclors 1016, 1242, and 1248 (ISDH 1994). Westinghouse did not use Aroclor 1248. However, degraded Aroclor 1242 can look like 1248. These Aroclors are partially comprised of more highly chlorinated PCBs, including several tri-, tetra-, and pentachlorobiphenyl congeners; however, most of the contaminated materials at the CD sites have most likely been under anaerobic conditions for several years, and anaerobic dechlorination of the PCBs in these materials may have occurred intrinsically. Between 1983 and 1987, clay caps have covered the contaminated materials at the Bennett Stone Quarry, Neal's Dump, and Neal's Landfill sites, and contaminated soils removed from the Anderson Road Landfill site are stored in the ISF in large piles. The cap-covered wastes and piled wastes are likely to be mostly anaerobic environments. Although the Lemon Lane Landfill site has been covered by a synthetic liner since 1987, several large conduits have been discovered beneath the landfill that may be providing oxygen to the landfill materials, resulting in localized aerobic conditions. Because the PCB-contaminated materials have not been characterized since 1984, an updated analysis identifying individual PCB congeners is needed to determine the degree of anaerobic dechlorination that has occurred intrinsically and the amount of further biological treatment needed. The tertiary lagoon sludge at the Winston-Thomas Sewage Treatment Plant site has been characterized more recently. However, the results of two separate evaluations do not completely agree. One of the evaluations was performed in 1992 by the City of Bloomington's contractor, Environmental Audits, Inc. (EAI). Based on analytical results of nine lagoon sludge samples and two drying bed sludge samples, EAI made the following observations and conclusions (EAI 1993): The average concentration of total PCBs and the total mass of PCBs in lagoon sludge samples decreased significantly compared to 1982 data because of aerobic biological destruction of the PCBs in the lagoon water and upper layers of sludge. The congener patterns in lagoon sludge samples were primarily Aroclor 1016, along with Aroclor 1242 and trace levels of highly chlorinated congeners present in Aroclor 1268. This situation most likely resulted from dechlorination of initial releases of high concentrations of Aroclor 1242 and low concentrations of Aroclor 1268. PCBs were virtually absent from drying bed sludges, which most likely resulted from complete PCB destruction during sequential exposure of the sludges to anaerobic conditions in the lagoons followed by aerobic conditions in the drying beds. In 1994, another evaluation of lagoon sludge analytical data was performed by Dr. John F. Brown Jr., of General Electric Company, an expert in the comparison of detected PCB congener patterns with normal PCB congener patterns. Based on congener-specific analyses of samples from the drying beds and lagoon, Dr. Brown concluded that only one drying bed sample had undergone appreciable biodegradation and that only select di- and trichlorobiphenyl congeners had been biodegraded in this sample. Dr. Brown also concluded that the lagoon samples contained almost pure Aroclor 1242, which was almost completely unaltered (Brown 1994). Although Dr. Brown's conclusions are believed to be more valid than the EAI results based on his expertise, both evaluations are based on the analysis of a limited number of samples; therefore, the amount of biodegradation that has occurred in the Winston-Thomas Sewage Treatment Plant site sludges requires a more thorough evaluation. Other information needed to implement this alternative includes the following: the types and quantities of amendments needed, the effectiveness of using indigenous bacterial strains, the use of amendments to stimulate biodegradation, the effectiveness of using inoculations with isolated strains, the rate of oxygen delivery during aerobic treatment, and the kinetics of anaerobic dechlorination and aerobic degradation. Treatability studies should be performed to test these conditions to determine the conditions that optimize biological treatment. The treatability studies should be conducted using representative samples of actual waste to be treated. In this way, it can be determined whether any contaminants in the wastes to be treated are toxic to the bacteria. The treatability studies should also evaluate whether sequential anaerobic-aerobic treatment is required at the sites or if enough intrinsic dechlorination has occurred so that only aerobic treatment is needed. Pilot-scale and laboratory-scale treatability studies should be conducted to determine how well laboratory conditions and results can be reproduced in the field. For CSPB, a pilot-scale study could involve constructing a single biotreatment cell and conducting tests on a smaller volume of soil than would be treated during full scale in multiple cells. During the preparation of this report, only one site could be identified at which pilot-scale sequential anaerobic-aerobic treatment in a biotreatment cell has been conducted, but these tests were inconclusive as of early 1994 (EPA 1994g). Pilot-scale testing could be conducted in situ at the tertiary lagoon using self-contained steel caisson reactors with mechanical mixers and injection systems, which were used during field studies at the Hudson River site (Harkness and others 1993). Another possible in situ pilot-scale design could involve partitioning off a small area of the tertiary lagoon and using mechanical mixers and pumps to mix, aerate, and inject amendments into lagoon sludges, which was performed at the French Limited Superfund site (DEVO 1992).