Updates on Demolishing the Bloomington ABB Plant
October 16-29, 2006
Week of October 16th
Building Demolition
- "New" 1994 boilers are to be removed from site by salvage company.
- "New" 1994 boilers are to be removed from site by salvage company.
-
Continue characterization and packaging of any remaining Universal
Wastes.
-
Continue disposal of PCB contaminated materials off-site.
-
Complete off-site disposal of asbestos (as long as disposal
contractor has available trucks).
-
Continue off-site disposal of special waste materials.
-
Continue sending scrap metal for recycling.
-
Continue general building demolition.
-
Perform air monitoring for PCBs as necessary.
-
Develop plan for draining, flushing and disposal of oils from the
transformers and other electrical components in the substation.
-
Treat and test additional storm water in water treatment system,
discharge as appropriate based on discharge limits.
Week of October 23rd
Building Demolition
-
Complete management of any remaining Universal Wastes.
-
Continue general building demolition.
-
Continue off-site disposal of special waste materials.
-
Continue to send scrap metal for recycling.
-
Treat and test additional storm water in water treatment system,
discharge as appropriate based on discharge limits.
|