Updates on Demolishing the Bloomington ABB Plant
May 1-15, 2006

Below is the schedule for the next two weeks for demolition work at our former manufacturing facility at 300 North Curry Pike Road.

Week of May 1st

Asbestos Abatement/Universal Waste Removal

Asbestos removal will begin in the second floor office area. Abatement activities will begin in the old boiler room and will continue in the original fan room. Removal of pipe wrap and transite will begin in the central portion of the building.

Building Demolition

Engineer to respond to bidders questions on the RFP. Bidder visits to continue.

Additional Sampling

Some additional roof samples and some samples of the water in the cistern will be collected.

Week of May 8th

Asbestos Abatement/Universal Waste Removal

Asbestos abatement activities to continue. Removal of asbestos in old boiler room will continue. Removal of pipe wrap and transite through the central portion of the building to continue.

Building Demolition

Addenda to the RFP to be prepared based on Bidder's questions and Site visits by interested bidders to continue. Engineer will respond to bidders questions on the RFP.

Additional Sampling

No additional sampling planned.

Warning! Eat no fish from Clear Creek, Pleasant Run, Salt or Richland Creeks.

Home
COPA

For more info, e-mail info@copa.org.
Copyright © 1990-2002 COPA, Inc. All rights reserved.
See legal page for terms of use and disclaimers.
All trademarks belong to their respective owners.