COPA Home

FIELD OVERSIGHT SUMMARY
NEAL'S LANDFILL SITE
SETTLING TEST

Tetra Tech EM Inc.
June 5 and 6, 2002
CIC info

INTRODUCTION

As requested by the U.S. Environmental Protection Agency (EPA) under Contract No. 68-W6-0037, Work Assignment No. 943-RSBD-0539, Tetra Tech EM Inc. (Tetra Tech) is conducting site visits and performing oversight activities at the Neal's Landfill site in Bloomington, Indiana. Viacom, Inc. (Viacom), is the responsible party for the site. PSARA Technologies, Inc. (PSARA), is Viacom's consultant. Earth Tech, Inc. (Earth Tech), is Tetra Tech's subcontractor and conducted a portion of the field oversight described herein.

As part of Viacom's screening of remedial alternatives for the site, a settling test was planned for surface water emerging from overflow springs at the site. The test was to be conducted during a storm event producing a surface water flow of at least 5,000 gallons per minute (gpm) created by an intense period of rain. The goals of the settling test were to evaluate ( 1 ) the fraction of polychlorinated biphenyls (PCB) remaining in a peak flow sample at various times after up to 24 hours of settling and (2) the fraction of PCBs remaining in a peak flow sample at various times after up to 24 hours of settling when an organo- clay flocculent was added to aid in settling.

This report summarizes settling test activities observed by Tetra Tech and Earth Tech at the Neal's Landfill site on June 5 and 6, 2002; issues and developments; and future activities at the site. Appendix A contains a photographic log of field activities, Appendix B contains a copy of Tetra Tech's field notes, and Appendix C contains a site location map. The attachment contains a copy of Viacom's test procedure for the settling test.

ACTIVITIES AND OBSERVATIONS

Tetra Tech's activities and observations at the Neal's Landfill site on June 5 and 6, 2002, are summarized below.

Wednesday, June 5, 2002

A storm event of sufficient magnitude to produce a surface water flow of 5,000 8pm from overflow springs at the Neal's Landfill site occurred during the afternoon of June 5, 2002. Viacom initiated the settling test at about 3:30 p.m. when it was certain that the 5,000-gpm flow rate would be achieved. A maximum flow of about 5,000 8pm was achieved from about 3:50 to 4:30 p.m. Viacom notified Earth Tech ofthe initiation ofthe test at about 5:00 p.m., and Earth Tech in turn informed Tetra Tech.

Earth Tech arrived at the Neal's Landfill spring treatment facility (STF) at 6: 10 p.m. Drums I through 6 had already been filled. The drums designated "A" did not have flocculent added, whereas the drums designated "B" had flocculent added as soon as the drums were full. Over the next 2 hours, the remaining four drums (A7, As, B7, and B8) were filled, and drums B7 and B8 were treated with flocculent. The approximate fill time for each pair of drums is presented below.

Drum Pair (A and B) Fill Time
13 :45 p.m.
24:10 p.m.
34:34 p.m.
45:03 p.m.
55:34 p.m.
66:04 p.m.
77:04 p.m.
88:03 p.m.

Drum pair I represents the true rising-limb storm sample. Flow was relatively constant as drum pairs 2 and 3 were filled. Drum pairs 4 through 8 were collected during the falling-limb portion of the storm flow.

At about 8:00 p.m., Earth Tech observed the addition and mixing of flocculent for drum B8. The flocculent was observed to be mixed at a constant rate, which was a deviation from the Viacom test procedure. This deviation is discussed further in the "Issues and Developments" section of this report. Earth Tech left the site at 8:30 p.m.

Having travelled to the site from its Louisville, Kentucky, office, Tetra Tech arrived at the STF at 9:00 p.m. At 9:10 p.m., PSARA read the staff gauge on the weir in Conard's Branch north of the site and reported the water elevation to be 0.78 foot (see Photograph No. 1). At about 9: 15 p.m., PSARA collected samples from drums B6 (3-hour sample), B7 (2-hour sample), and B8 (1-hour sample). At about 9:30 p.m., PSARA collected the 4-hour sample from drum A5, and at about 9:45 p.m., PSARA collected the 4-hour sample from drum B5. At about 10:00 p.m., PSARA collected samples from drums A6 (4-hour sample), A7 (3-hour sample), and A8 (2-hour sample). At about 10:20 p.m., PSARA collected samples from drums B6 (4-hour sample), B7 (3-hour sample), and B8 (2-hour sample). At about 11:00 p.m., PSARA collected samples from drums A7 (4-hour sample) and A8 (3-hour sample). At about 11:20 p.m., PSARA collected samples from drums B7 (4-hour sample) and B8 (3-hour sample). At about 11:45 p.m., PSARA collected the 8-hour samples from drums A I and B I . Because the sampling was repetitive in nature and was to be completed in accordance with a schedule, Tetra Tech left the site at 11:50 p.m.

Thursday, June 6, 2002

Earth Tech arrived at the Neal's Landfill site at 7:40 a.m. At that time, the staff gauge on the Conard's Branch weir showed a water elevation of 0.74 foot. Earth Tech left the site at 7:50 a.m.

Tetra Tech arrived at the STF at 7:50 a.m. At about 8:00 a.m., PSARA collected the 12-hour sample from drum A8, and at about 8:25 a.m., PSARA collected the 12-hour sample from drum B8 (see Photographs No. 2 and 3). PSARA reported that drum sampling would not resume until about 3:45 p.m., when PSARA would begin collecting the 24-hour samples from the 16 drums. The final 24-hour sample would be collected at about 8:25 p.m. Before leaving the site, Tetra Tech took photographs of the settling test setup (see Photograph No. 4) and the storm wiser overflow collection point (see Photograph No. 5). PSARA and Tetra Tech left the site at 8:45 a.m. Because the remaining sampling was repetitive in nature and was to be completed in accordance with a schedule, Tetra Tech did not return to the site to observe the collection of the 24-hour samples.

ISSUES AND DEVELOPMENTS

Richard McCandless of PSARA initially reported that the storm event on June 5, 2002, was not expected to produce the required 5,000-gpm flow in Conard's Branch. Because of PSARA's need to respond quickly to the site when it became apparent that the storm event would produce the required flow, Earth Tech and Tetra Tech were not notified of the initiation of the settling test until about 5:00 p.m. on June 5 and were not able to respond to the site until six of the eight drum pairs had been filled and drums B I through B6 had been flocculated. Proper addition and mixing of flocculent constituted the most critical element of the settling test. Earth Tech did observe the mixing of flocculent in drum Be, which was conducted at a steady rate for 20 minutes. This activity was not conducted in accordance with the Viacom test procedure, which requires mixing at various rates (high, medium, and low) for varying periods of time (see the attachment, Section C, Step 15). The effect of PSARA's modified mixing procedure on the test results likely cannot be quantified. Test results will be available approximately one month after completion of the settling test. All other settling test activities observed by Earth Tech and Tetra Tech, including all the sampling procedures, appeared to conform to the Viacom test procedure.

FUTURE ACTIVITIES

Tetra Tech will continue to conduct site visits and perform oversight and sampling activities at the Neal's Landfill site as directed by EPA.
Warning! Eat no fish from Clear Creek, Pleasant Run, Salt or Richland Creeks.

Home
COPA

For more info, e-mail info@copa.org.
Copyright © 1990-2002 COPA, Inc. All rights reserved.
See legal page for terms of use and disclaimers.
All trademarks belong to their respective owners.