Test Report for LF6 Flush and Storm Dye Testing at Lemon Lane
Landfill
April and May 2002
1.0 Flush Test of LF6-8" Piezometer
1.1 Test Description
On April 10, 2002 at 10:00 hours 1032 gallons of water was flushed into
Piezometer LF-6-8" along with 50 grams of Fluorescein dye. Approximately 5
feet of head was induced in the piezometer and presumably the gravel pit in
which it is installed. It took 10 minutes to flush the water in. Water levels were
measured by hand in MW-15 every 15 minutes for the first hour and hourly for 8
hours after. Transducers recording water levels every 5 minutes were installed in
wells:
MW-21, MOO-6, NN-12, NN-300A, KK-112
The following wells were sampled for dye hourly for the first 8 hours and then
daily for 5 days:
MW-4s, PZ-F, NN-300, 00-30O, 00-300A, 00-370
Illinois Central Spring was sampled at its emergence with auto samplers on an
hourly schedule.
No rain had occurred for several days before the flushing, nor in the 24 hours
immediately following the flushing.
A copy of the test plan is included as attachment 1.
1.2 Test Results
Table 1 shows the dye results at the wells monitored and Table 2 (part 1 and part 2) shows the dye results at the spring along with the PCB results of select samples at the spring.
Figures 1A, 1B, 1C, 1D, &1E show the datalogger results.
The water flushed into LF-6-8" reached the phreatic zone in one hour and raised the phreatic zone about 0.05 feet (less than an inch). Note that well KK-112,
which is much closer to the IC Spring than the landfill and historically maintains a
water level significantly above most of the landfill phreatic wells, also responded.
This indicates the higher water level in this well is not caused by an isolated
perched zone.
Distinct dye breakthrough curves were seen in wells 00-370 and 00-300A. The results in wells MW-5S, PZ-F, and NN-300 are less distinct. No dye was
detected in 00-300. The apparent appearance of dye in all wells within an hour
of flushing may be the hydraulic flushing of residual dye or an analytical anomaly.
The first unambiguous appearance occurred in well 00-370 in 3 hours or less
and peaked at 6 hours after flushing. The first unambiguous appearance in OO-
300A occurred 7 hours after flushing.
Figure 2 is a plot of the dye and PCB concentration as detected at lil inois Central
spring. The first appearance of the dye occurred 11 hours after injection. A
clear, single peak breakthrough curve peaking at 387 ppb at 13 hours after
flushing is shown. This travel time of 11 hours is almost exactly what would be
predicted for PCB peak storm travel time based on the average spring flow
observed (240 gpm) during this test. This is different than previous dye test
conducted from LF6 that showed a lag time of up to 7 hours between predicted
and actual travel times and showed double peak breakthrough curves.
The PCBs at IC Spring were not significantly elevated during the time dye arrived
at the spring. Although free product had been detected at the LF64 location
within two weeks prior to the flushing, apparently little to no PCBs were mobilized
during the flushing. Also note that the apparent mass recovery of dye at IC
Spring was about 70 grams. With 50 grams injected, this indicates some
measurement error, and also indicates that there was no significant storage of
the dye injected.
Table 3 shows the water level in LF6-8 after water injection. The LF6 pit (gravel
filled) dimensions are approximately 7' by 12'. Immediately after injection the
water level had risen approximately 5 feet. The water took almost 9 hours to
completely drain from the pit. This is an average outflow rate of about 2 gpm.
Maximum outflow rate appears to be approximately 4 gpm.
2.0 Storm Tracer Test from LF64" Piezometer
2.1 Test Description
On May 6, 2002 300 grams of Fluorescein dye was injected with 10 gallons of
flushing water in piezometer LF6-4" at 13:10 hours. This took place at the
beginning of a 0.43" storm event. Dye was monitored at the spring on 10 minute
intervals until 20:00 hours and thereafter hourly using auto samplers. Samples
were also taken in wells:
MW-4s, PZ-F, NN-300, 00-300, 00-300A, 00-370
Samples were taken every 15 minutes until 19:30 hours. The hourly samples for
dye at the spring were continued until 5/9/02 9:00 hours through 2 successive
storm events.
Based on the dye results, select samples from the spring and wells were
submitted for PCB analysis. Dataloggers measured water levels in LF64n, MW-
21, and MOO-6 on five minute intervals.
A copy of the test plan is included as attachment 2.
2.2 Test Results
Figure 3 shows the rainfall record and the level response in LF6-4". It took nearly
30 minutes for this water to leave the piezometer, a flow rate of 0.3 gpm. The
piezometer seemingly did not respond to the first 0.43" rain. The response to
even the third 1.14" rain was only a maximum of 0.95 feet. The lack of response
of LF6-4" to the first rain is confirmed by the fact that no dye concentrations were
detected above background levels in the monitoring wells that were sampled or
at IC Spring. Monitoring well sampling did not continue past 19:30 hours on May
6. Table 4 shows the PCB results for the monitoring wells. Table 5 shows the
conductivity and dye results from the wells.
Figure 4 is a plot of Illinois Central spring flow, dye concentration and PCB
concentration at the spring. The first rain induced a PCB peak of 20 ppb but no
dye peak. The 2nd and 3 rains induced sizable PCB and dye peaks, but when
the PCB peaks are arriving at the spring the dye concentration actually
diminishes. This indicates the water arriving at the spring is high in PCBs but low
in dye. Dye peaks are delayed 6 and 5 hours respectively from the PCB peaks in
storms 2 and 3.
Table 6 shows summary data for the IC Spring. Note that the total dye recovered
was approximately 337 grams. With 300 grams injected this indicates a lessor
amount of measurement error than for the flush test. Approximately one third of
the dye injected on 5/6/02 was recovered as a result of the 5/7/02 storm and the
remaining two thirds was recovered from the 5/8/02 event.
3.0 Conclusions and Implications for Further Work
3.1 Conclusions
- Some of the dye from the LF6 flush test was again confirmed to travel
southwest into Valhalla Cemetary. Dye was not conclusively detected at
well MW4S. Wells NN300 and 00300 did not receive unambiguous dye
detections. These wells are screened in the 795-800 foot zone, while
their paired uncreened and shallower neighbors (00300A and NN300A)
and 00370 (another open hole well) received dye. This indicates th e dye
may be traveling in an upper epikarstic zone.
- Flushing LF6 during non-storm conditions did not induce a PCB peak
response at IC Spring.
Some of the flushed water from LF6, when a high hydraulic head is
induced, reaches the phreatic zone within one hour and induced a
response even as far away as KK112.
- The outflow rate from the LF6 conduit averaged about 2 gpm.
- Based on tracer travel time and amount of hydraulic response during
storms, the LF6 area is not the immediate contributing source to the high
PCB pulse that manifests at the spring during storm flows.
3.2 Implications for Further Work
- Dye flushed from LF6 arrives in Valhalla wells near NN300A and 00370.
This area of Valhalla should be further investigated to see if more PCBs
can be found at these locations. Although high levels of PCBs were not
associated with the LF6 flushes, the dye results may indicate that this area
of Valhalla is near a major pathway from the southeast corner of the site
where PCBs may be stored in other reservoirs. Samples taken above the
water table from NN300 and NN300A during drilling had high
concentration of PCBs.
- It appears that the dye travel from LF6 to the southwest may be occurring
in an epikarst zone. Review of the drilling and videologs for these area
reveals conduit development between 818 and 823 feet amsl. One well,
00300A, maintains a water level in this range and it received dye on all
LF6 dye tests. Well 00370 also received dye during all dye test from LF6
and it is an open hole so the dye arriving at that well could be traveling at
any elevation (less than 833 the top of rock at 00370). Well NN300A also
received significant dye in other dye test (it was not sampled in this test).
NN300A is an open hole well bottomed at about 810 feet amsl. Well
00370 was pump tested during 1999 and PCBs dropped during the pump
test. This may indicate that the PCBs entering the well (like the dye) is
coming from an epikarst fracture and being diluted by the phreatic water
present in the well. The "A" series Valhalla wells should be modified to
reflect only epikarst water levels (as 00300A does now), and isolate them
from the phreatic water.
- Perform additional flush and tracer tests during non-storm conditions.
Candidates include the shallow Valhalla wells after they are
modified/isolated, PZF, and the railroad tracks.
- Consider additional shallow wells at the southeast corner of the landfill
that could be located on existing geophysics anomalies and that may
intercept the lower epikarst zones around the 823 elevation.
|