COPA Home

Lemon Lane Final Report
June, 2001

1.0 Introduction | 2.0 Site Description and History | 3.0 Remediation Planning | 4.0 Changes to Original Work Plan | 5.0 Sampling Activities | 6.0 Preparation of Iterim Cap Surface | 7.0 Intallation of the Geosynthetic Clay Barrier | 8.0 Placement of Geomembrane and Geonet | 9.0 Placement of Vegetative Support Zone | 10.0 Site Surface Water Controls | 11.0 Site Restoration | 12.0 Data Validation | Photos

9.0 PLACEMENT OF VEGETATIVE SUPPORT ZONE

9.1 Inspection and Quality Control

The function of the vegetative support zone is to promote vegetation, minimize erosion, promote drainage and protect the cap barrier materials. Design details in the WP require that the support zone consist of 6 inches of topsoil and 18 inches of cover soil over the geonet drainage composite system. These two zones were constructed separately. The soil characteristics for the cover soil require a medium textured material containing sufficient sand to allow drainage to occur and sufficient clay/silt to allow some water to be retained for vegetation support. Samples were taken of the cover soil at the source prior to excavation and transportation to the site for placement. The samples were sent to Golder Associates for analysis and approval for use as cover soil. The results are reported in PSARA Construction Certification Report contained in Appendix F.

9.2 Placement of Cover Soil

The 18 inches of cover soil were obtained from Hanna Trucking and met the specifications for cover soil as identified in the Final Cap Design Report. Cover soil was delivered to the site in over-the-road tri-axle dump trucks, dumped loose on the slopes, and spread over the slopes by a Komatsu D65 dozer. Truck access to the cap area was over two culverts installed to cross over the perimeter channels on the east and the northwest. Support soil was placed in one loose uncompacted lift. Care was taken to insure that both the dump trucks unloading soil and the dozer spreading the soil tracked only over previously spread cover soil that was not less than 12 inches thick. No density specification was provided in the project specifications and no formal density testing was performed. Since cover soil was placed and spread over the entire landfill, construction traffic was fairly uniform over the entire landfill. As a result, construction traffic provided adequate compaction to ensure the stability of the cover soil layer. The cover soil terminated at the edge of the cap into a geotextile fabric that was placed between the cover soil and the riprap. The geotextile prevents cover soil from eroding into the riprap.

Both Golder and PSARA representatives provided oversight and certification inspection services for the placement of the vegetative support zone soils over the geomembrane/geonet system. Continuous inspection of cover soil placement was performed in order to insure that construction equipment did not drive directly on the geonet drainage layer, and that wrinkles in the geonet were minimized.

Once the 18 inches of support zone soil was in place, purchased topsoil was brought to the site using the same tri-axle dump trucks to complete the vegetative support zone. Prior to delivery the topsoil was analyzed to insure it met the topsoil specification stated in the Final Design Report. The same process for spreading the support zone soil was used for the topsoil.

Survey certification of the thickness of cover soil was performed by SNA using the same 50 ft. by 50 ft. grid system that was used to verify the thickness of the cushion soil. A tabulated summary of survey results is included on Figure 9. This table was prepared by SNA and shows a cover soil thickness of at least 24 inches at all 50 ft. by 50 ft. grid points on or within the LOO except at point number 159. At this point the cover soil was only 1.6 feet. This deficiency in thickness will be corrected in the spring of 2001 when the weather permits. This table also lists the final elevations at these grid locations.

PSARA's certification letter describing cover soil placement and the integrity of the geomembrane/geonet system is presented in Appendix G of this report. In summary, the letter states that the cover soil layer was placed in general accordance with the project specifications. No visible damage was observed to the geonet drainage composite or the underlying geomembrane liner as a result of soil placement or the movement of construction equipment on the cap.


Warning! Eat no fish from Clear Creek, Pleasant Run, Salt or Richland Creeks.

Home
COPA

For more info, e-mail info@copa.org.
Copyright © 1990-2002 COPA, Inc. All rights reserved.
See legal page for terms of use and disclaimers.
All trademarks belong to their respective owners.