Lemon Lane Final Report
June, 2001
1.0 Introduction | 2.0 Site Description and History | 3.0 Remediation Planning | 4.0 Changes to Original Work Plan | 5.0 Sampling Activities | 6.0 Preparation of Iterim Cap Surface | 7.0 Intallation of the Geosynthetic Clay Barrier | 8.0 Placement of Geomembrane and Geonet | 9.0 Placement of Vegetative Support Zone | 10.0 Site Surface Water Controls | 11.0 Site Restoration | 12.0 Data Validation | Photos
8.0 PLACEMENT OF GEOMEMBRANE AND GEONET
8.1 Inspection and Quality Control of Geosynthetics
Geosynthetics used in the construction of the RCRA Subtitle C cap consisted of a
40 mil thick textured very flexible polyethylene (VFPE) geomembrane liner, and a
Geocomposite drainage medium with a geonet component composed of virgin high-
density polyethlene resin (HDPE) wire mesh with non-woven geotextile fabric
bonded to both sides. The VFPE is a broad classification of materials, which
includes linear low density polyethylene (LLDPE), low density linear polyethylene
(LDLPE), and very low density polyethylene (VLDPE). Each roll of LLDPE material
delivered to the site was identified with a tag that included the lot number, roll
number and date of manufacture.
Each of these cap components was subject to strict strength and performance
specifications and was inspected upon delivery and during placement. Production
QC tests were performed by Agru / America, Inc., the manufacturer, and were
submitted to WAS at the time of delivery.
The manufacturing QC tests performed on the geomembrane material include:
- Tensile Properties
- Core Thickness
- Puncture Resistance
- Tear Resistance
- Dimensional Stability
- Carbon Black Dispersion
- Carbon Black Content
- Coefficient of Friction
- Low Temperature Brittleness
- Density
The manufacturing QC tests performed on the Geocomposite material include:
- Flow Capacity
- Transmissivity (Geocomposite)
- Permittivity (Geotextle)
- Mechanical Properties
- Grab Tensile Strength (Geotextile)
- Apparent Opening (Geotextile)
- Peak Tensile Strength (Geonet)
- Play Adhesion (Geocomposite)
- Coefficient of Friction
- Material Properties
- Polyethylene Density (Geonet)
- Carbon Black Content (Geonet)
- Dimensions
- Thickness (Geonet)
- Mass/Area (Geotextile)
Each submittal was reviewed and approved by Golder Associates. The quality
control review of these submissions is discussed in detail in the Golder Certification
Report contained in Appendix F. In addition, Viacom representatives obtained
samples periodically from the material delivered to the site. Golder conducted
quality control testing on these samples to insure that the material performance
matched the QC test results provided by the manufacturer. General inspection of
these materials at the job site prior to deployment involved the matching of the
manufacturer's Lot and Roll numbers that were tested, with those that were actually
delivered to the site. These records are also included in the Golder report.
8.2 Geomembrane Panel Layout and Survey Documentation
Following the completion of a "Geomembrane Installer's Certification of Subsurface
Acceptability" form for each area (Appendix lil of report in Appendix F), individual
geomembrane panels were deployed over the slopes, cut to length and then fusion
welded together over the full length of adjoining panel sections. Installation of the
geomembrane started on the northeast and proceeded across the north slope.
Once the north slope was completed the installation operation moved to the
southeast and proceeded across the south slope. The geomembrane liner was
deployed in panels approximately 23 ft. wide and 492 ft. in length. Dual-sided
textured VFPE geomembrane was used over the landfill and extended into and
through the perimeter channels. The textured geomebrane was also extended over
the southwest slope, across the bottom of the retention pond and up the west bank
of the retention pond. Smooth surface VFPE geomembrane was not used. The
textured geomembrane was secured into an anchor trench that was constructed on
the outside perimeter of the channel and retention pond. Placement of the GCL and
the geomembrane over the surface of the consolidated materials was completed on
November 11, 2000. The general configuration and arrangement of the panels was
established in the field based on the final as-built shape of the landfill. An as-built
panel layout drawing for the geomembrane covering the landfill was prepared by
Envirocon and is included as Figure 10.
The as-built drawing shows the general configuration of individual panels over the
top of the GCL, as well as survey data locating several panel intersection points.
The panel layout survey data were developed by SNA and provided to Envirocon.
This drawing also documents the individual panel and roll numbers, the locations of
butt seams (panel end to panel end; square on relatively flat areas and diagonal on
the slopes), the locations of CQA seam tests and repairs, and the extent of liner
deployment beyond the LOC through the perimeter channels. In all cases, the
geomembrane was extended into an anchor trench that was excavated around the
perimeter channel about two feet beyond the outside edge of the channel. A trench
was also excavated on the west and south edges of the retention pond. The
purpose of the trench was to terminate the edge of the geomembrane, thus securing
the RCRA cap. Other details regarding the geomembrane deployment are
contained in the Golder CQA Certification Report for the cap in Appendix F.
8.3 Penetration Boots and Geomembrane Repairs
Penetrations through the geomembrane were made at each of the 6 new
piezometers shown on Figure 8. Four piezometers were located within the LOC and
two were just outside the limits between the consolidation and the perimeter channel
on the west side of the site. All six piezometers penetrated the geomembrane. At
each location, a penetration boot was fabricated in the field and installed around the
base of the piezometer riser pipe. The boot was extrusion welded to the
geomembrane panels at the base of the riser. A neoprene gasket material was
placed between the boot and the riser pipe and two stainless steel hose clamps
were used to clamp the boot to the pipe. This approach was necessary since it was
not possible to extrusion-weld the VFPE boot directly to the PVC pipe due to
incompatibility of these materials. Caulking was applied to the seam between the
geomembrane and the PVC pipe.
Repairs were made to the geomembrane anytime the integrity of the membrane was
in question or when testing of a seam was required. All repairs involved a patch
being made from the same geomebrane material and having the patch extrusion
welded to the membrane. Repair information and CQA of repairs is discussed in the
Colder CQA Certification Report in Appendix F.
8.4 Geonet Drainage System
The geonet is a general drainage component of the cap. The geonet drainage
composite system consists of a HDPE drainage grid sandwiched between two layers
of non-woven geotextile fabric. The geonet drainage composite was placed over the
entire cap and extended into the riprap contained in the drainage features around
the perimeter of the LOC. The geonet composite was deployed in panels, much like
the geomembrane, except that individual panels were overlapped 1 foot and spliced
together using plastic zip-ties spaced 5 feet apart. The function of the geonet is to
collect infiltration water that percolates through the vegetative support zone soils.
The water collected in the drainage grid flows through the grid into the perimeter
channel. The drainage net extends into the riprap that lines the channels and the
bench between the retention pond and the LOC on the west.
|