Lemon Lane Final Report
June, 2001
1.0 Introduction | 2.0 Site Description and History | 3.0 Remediation Planning | 4.0 Changes to Original Work Plan | 5.0 Sampling Activities | 6.0 Preparation of Iterim Cap Surface | 7.0 Intallation of the Geosynthetic Clay Barrier | 8.0 Placement of Geomembrane and Geonet | 9.0 Placement of Vegetative Support Zone | 10.0 Site Surface Water Controls | 11.0 Site Restoration | 12.0 Data Validation | Photos
5.0 SAMPLING ACTIVITIES
5.1 Post-Excavation Grid Sampling
Verification sampling and analysis was conducted in all excavation areas to
determine whether the cleanup criteria had been achieved. Sampling and analysis
was performed per the Post-Excavation Sampling and Analysis Plan (SAP) which is
contained in Appendix D of the LL WP.
Most post-excavation grid sampling was specified in the SOW to be performed using
the 50-ft. by 50-ft. grid system previously established for delineation and excavation.
Sample collection, quality assurance testing and data interpretation methods were the
same as those used during the pre-excavation perimeter delineation sampling
program, as reported in Appendix A of the LL WP.
In general, the post-excavation sampling of each 50 ft. by 50 ft. grid consisted of the
collection of four samples from the centers of four 25 ft. by 25 ft. subgrids. The four
samples were composited and then analyzed, or each sample was analyzed
individually by EPA method of 8082.
Verification samples were collected at a O to 6 in. depth intervals. If the analytical
result for the composite from the initial depth interval was greater than the clean criteria
for that grid, the grid was re-excavated and the verification sampling was repeated. In
many cases each of the four samples from that depth interval would be analyzed
individually in an attempt to identify the specific location that required re-excavation. In
a few cases this approach was used on subgrids as small as 12.5 ft. by 12.5 ft. (1/16th
of a full 50 x 50 grid). The sampling protocol was applied until the contamination had
been isolated to one or two subgrids. All grid or subgrids were thereby sampled,
tested, excavated and re-sampled until the clean criteria for that area was met.
In some cases further excavation or sampling was impractical due to the removal of
material down to bedrock. In these cases the government oversite parties were
consulted and no further excavation was attempted. No verification sampling was
performed in bedrock excavations since no appreciable material remained to sample.
Tables 1 and 2, and Figure 4 show grids or subgrids that were excavated to bedrock
as BR. All bedrock excavations were backhiled with at least 6 inches of clean
compacted clay.
In the southwest part of Area 24, where borings were performed to further delineate
FGH/16-17 grids, pre-excavation boring results were used as the verification result.
These boring sample results and the agreement made to use these results for
verification samples are discussed in Appendix A.
Sidewall sampling was performed on the northern sidewall of the hot spot excavation
contours, east of the 31011 ODE line. Sidewall sampling was performed on each 25 ft
length of sidewall per the LL WP SAP. To expedite the sidewall excavation, borings
were drilled and sampled to find the extent of the PCB contamination requiring
excavation. Borings were drilled on a ten foot spacing extending north from the
sidewall excavation for each 25 foot subgrid. The waste contained in the boring down
to a four foot depth from the surface was composited into a sample and analyzed. The
sidewall was excavated back to the hrst boring sample that met the clean up
requirement and past the visual standard.
The clean criteria for post-excavation grid sampling varied based on location on the
site. All areas had a maximum PCB level for an individual grid as well as a maximum
level for the arithmetic average for all grids within an area. Allowable area averages
were increased by providing ten inches of clean cover over the grids. Table 1 of
Appendix A of the LL WP lists the clean up criteria for various areas of the LL site.
The clean criteria for all areas within the hot spot excavation contours, including the
northern sidewall hot spot excavation contours, east of the 31011 00E line, was
'100 ppm for individual grids with an average for the areas not to exceed 50 ppm.
Areas outside of the LOC had various clean up criteria based on future access to the
area (inside or outside the fence) and whether the area was considered residential or
not. Areas outside of the security fence, except on the south perimeter, were required
to have a maximum individual grid sample result at less than 5 ppm with an arithmetic average
for all grids in the area at less than 5 ppm if ten inches of cover were used or at 2 ppm if no
cover was used. Areas inside the security fence and outside of the LOC, except on the
south perimeter, were to be cleaned up to a maximum of 20 ppm for an individual grid
with an area average of less than 10 ppm with ten inches of cover.
The south perimeter outside of the LOC had a less stringent standard. Individual grids
were cleaned up to less than 35 ppm. The average of all grids in these areas is to be less than 20 ppm.
Individual grids that were more than 5 ppm in which the soils are accessible to people were
covered with 10 inches of clean soil cover.
Table 1 of the LL WP summarizes the cleanup criteria, grid size and cover
requirements for each of the areas that required excavation and verification
sampling under this project. Figure 5 shows the locations of these areas within the
site plan. All final post-excavation grid sampling results are shown by grid or subgrid
on Figure 4 and also presented by area in Table 1. The arithmetic average for each
area is also listed in Table 1.
5.2 Personnel Monitoring
Personnel monitoring was performed to evaluate worker exposure to PCBs, VOCs,
asbestos, and lead and to ensure that these exposures did not approach the
threshold limit values (TLVs) or permissible exposure limits (PELs) for each of these
substances.
Personnel exposures were evaluated by using personnel sampling pumps in
accordance with NIOSH Method 5503 for PCBs, NIOSH Method 1501 for benzene,
toluene, ethylbenzene, and xylenes, NIOSH Method 7400 for asbestos, and NIOSH
Method 7300 for lead. These methods use small, portable air sampling pumps that
are worn by workers. Polychlorinated biphenyl samples are collected on a Florisil-
containing sampling medium preceded in line by a glass fiber filter. Both the Florisil
tube and the filter are submitted for laboratory analysis. Samples for VOC analysis
are collected in a solid sorbent (charcoal) tube. Samples for asbestos and lead
analysis are collected on a cellulose ester membrane filter. To quantify worker
exposures, the samples are collected in the personal breathing zone of workers for a
duration of at least 7 hours.
Exposure monitoring was performed on site personnel working in excavation areas.
These activities included capacitor removal, capacitor loading, grid excavation,
waste excavation, and consolidation. Table 7 summarizes the samples and results
collected from the site. Samples were collected for various constituents at the
discretion of the health and safety coordinator, based upon work activities and
corresponding hazard.
The health and safety officers on site monitored site operation procedures and the
resulting personnel monitoring sample results, especially in the capacitor handling
operations. Changes were implemented to worker operations as needed to keep the
exposure levels low.
The results of all personnel monitoring at the site show that all personnel exposures
to PCBs, asbestos, lead, benzene, toluene, xylenes and ethylbenzene during site
activities were below the designated action levels, TLV's, and PEL's.
5.3 Perimeter Air Monitoring
Perimeter air sampling was performed to ensure that excavation and material
handling operations did not result in excessive airborne PCB emissions from the
site. Air samples were collected using modified polyurethane foam (PUF) samplers
in accordance with USEPA Method T-04 and the site-specific Air Monitoring Plan
(AMP) dated, April 28, 2000. Air samples were analyzed to determine the
concentrations of PCBs at the boundaries of the LL Landfill site during excavation
operations. Perimeter air monitoring was conducted by PSARA.
Air monitoring stations were originally located at five locations, north, west, south,
east and southeast along the perimeters of the site as described in the AMP.
Figure 5 shows the PUF sampler locations throughout the project. Sampling was to
be conducted only on days when material handling or excavation took place.
Per the LL WP, background samples were taken at all PUF locations before the start
of excavation. Background samples on April 19 and 20 were analyzed. The highest
background sample result obtained was from the south sampler on April 19. This
sample result was 57.8 ng/m3.
Per the LL WP,one sample representing the prevailing down-wind direction was to
be selected each day for analysis at an offsite laboratory. A meteorological station
was installed and operated at the site in order to determine prevailing wind direction
and weather information. Before the start of excavation at LL, Viacom agreed to
analyze the southeast sample (near the Griffin Property) each day along with the
sample in the prevailing wind direction. Daily PUF sampling began on May 17 when
excavation began as discussed in Section 4.5.1.
In the beginning of June, high PUF results were experienced as discussed in
Section 4.5.2. A dust control program, including a clean clay cover over the
consolidation pile, resulted in a reduction in air emissions. Starting on June 5, all
PUF samplers closest to the neighboring residents were analyzed daily. This
included the east, southeast and north PUF samples. If the daily prevailing wind
was different than these three directions, it was also analyzed.
After the July shutdown as discussed in Section 4.5.5.1, Viacom agreed to add three
new PUF samplers in the residential neighborhood to the north and east of the LL
site. On August 8 the Woods, Bender and Gray St PUF samplers were put into
service. The locations of these three samplers are shown on Figure 5. The
addresses of residents where the three new PUF samplers were installed are:
Joyce Woods, 947 N. Lemon Lane
Bender Lumber, 2051 W. Vernal Pike
D. J. Sparks, 1720 Gray Street
Up until the July shutdown, sample results were reported two days after the sample
was collected. When excavation restarted on August 16, PUF results were obtained
for all locations and sample results were expedited so that results were reported the
day after the samples were collected.
On August 15, a PUF sampler was located on the Moore property, about 60 feet to
the east of the Griffin property. This sampler was installed to take the place of the
southeast sampler for use when the Griffin property excavation began. Both the
Moore and the southeast sampler were operated and the samples analyzed from
August 15 until August 24 for comparison. Therefore, a total of nine PUF samples
were analyzed each day during this period.
The Moore sampler was deactivated when it was decided to relocate the southeast
sampler to the eastern property line on the Griffin property. The southeast sampler
was relocated to the Griffin east fence line on September 1, as shown on Figure 5.
This PUF location is referred to as the Griffin location on the air sampling log.
A new south PUF sampler was installed on September 5. The new location was
300 feet south of the old south location, away from the tree line and into the
cemetery, as shown on Figure 5. The new PUF location is referred to as the
Valhalla sample location on the air sampling log. The sampler at the old south
location was operated and the samples analyzed until September 12, along with the
new Valhalla sampler for comparison. After September 12 the old south PUF
sampler was removed.
At the September 19 weekly meeting the government parties gave approval to return
to the 48 hour turnaround of PUF sample results instead of the expedited overnight
turnaround. All eight PUF samples for each day were still being analyzed.
On October 1, the Valhalla PUF sampler was relocated approximately 400 feet east
and 100 feet north, as shown in Figure 5. This PUF sampler was relocated at the
request of the cemetery, as the excavation moved toward the southeast corner of
the site. The new PU F location is referred to as the Valhalla east sample location on
the air sampling log.
On Friday, November 3, the operation of the three neighborhood PUF samplers,
Woods, Bender and Gray Street, was discontinued with the approval of the EPA.
The remaining five perimeter PUF samples were still analyzed each day. On
November 9, the number of PUFs analyzed was further reduced to only the primary
wind direction each day and the secondary wind direction when a significant
secondary component was recorded.
PUF sampling was discontinued on November 13, when all site operations related to
waste handling were completed and all exposed waste surfaces were covered.
The five perimeter PUF samplers were run again to obtain background samples after
the project was completed. Samples were analyzed for the north, east, south, west
and Griffin sample locations on December 5, 6 and 7. All results obtained during
these days were less than 7 ng/m3.
In summary, Viacom collected high volume air samples while the excavation and
consolidation of waste was being conducted. Samples were collected and analyzed
from May 17, 2000 to November 13, 2000. Additionally background samples were
taken prior to excavation on April 19 and April 20, 2000 and also on December 5, 6,
and 7 Table 5 presents all the perimeter air sample results obtained for the LL
Landfill site.
5.4 Voyager VOC Sampling
Real time sampling for volatile organic compounds (VOCs) was performed using a
Photovac Voyager portable gas chromatograph (GC). The unit was calibrated daily
for 8 VOCs. Three were specified in the LL WP, trichloroethene (TCE),
tetrachloroethene (PCE)andvinyl chloride. In addition, the unit was calibrated for
benzene, ethylbenzene, m-xylene, p-xylene and o-xylene.
The Voyager was typically located at the fence line on the east side of the LL site,
which was generally the downwind direction. This location was also the closest to
the local residents. Early in the project the unit was moved to monitor other
locations, however this was discontinued in favor of monitoring nearest to the local
residents. The unit operated on batteries that lasted about 4.5 hours per charge.
Typically 8 to 10 low volume air samples were taken daily during the hottest part of
the day. The unit was kept in an insulated box containing ice packets to reduce the
ambient operating temperature during the extremely hot days. The unit was not run
on rainy or extremely damp days.
Sample duration lasted 20 seconds with an analysis time of 20 minutes after which
the unit purged for 10 minutes prior to the next low volume sample occurring. No
significant levels of VOCs were detected throughout the project and location made
no difference in detection. Operation of the Voyager was discontinued on
October 18.
5.5 Wastewater Sampling
A wastewater treatment plant was mobilized and constructed at the southwest corner
of the site by WRS in accordance with the WP. The system consisted of 250,000
gallon portable influent holding tanks, 250,000 gallon portable effluent holding tanks
and associated carbon vessels, pumps and transfer hoses.
A total of 35 batches of storm water runoff were collected and pumped to the influent
tanks. These 35 batches represent a total of 865,000 gallons of storm water treated in
the wastewater treatment system. The treated water was used for dust control on haul
roads and excavations inside the LOO or discharged to Sargent's Pond.
Prior to releasing each batch of treated water, the water was sampled. The sampling
consisted of the collection of a 1-liter amber jar of treated water from one of the effluent
holding tanks. The sample was shipped under chain-of-custody control to Heritage
Environmental Laboratories in Indianapolis, Indiana. Analysis was performed to reveal
if the sample was below the .3 ppb PCB limits required by the SOW. Table 10 lists
each batch of water that was treated and released or used for dust control.
5.6 Groundwater Monitoring
As indicated in Section 3.7, Viacom implemented an interim surface and Groundwater
monitoring program at area springs and residential wells around LL Landhil per the
requirements of the SOW. Illinois Central (ICE), Quarry (ICQ) and Slaughterhouse
(SL) Springs, Sargent's Pond and two residential wells were monitored. Interim
monitoring was performed before, during and after excavation and consolidation
activities. Groundwater samples, and residential and spring water grab samples were collected
in accordance with approved sampling protocols, including the measurement of
water levels, purging and the measurement of purge parameters, where applicable.
For quality assurance purposes, duplicate, matrix spike, and field blank samples
were collected and analyzed. All samples were labeled, logged onto chain-of-
custody forms, stored on ice and transported in insulated coolers to Heritage
Laboratories of Indianapolis, Indiana or Antech Laboratory in Export, PA for analysis
of PCBs using EPA Method 608/SW-846, Method 8082, and a detection limit of
0.1 parts per billion (ppb). Other field measurements and PCB analytical results for
these sampling events are summarized in Table 9.
|