Lemon Lane Final Report
June, 2001
1.0 Introduction | 2.0 Site Description and History | 3.0 Remediation Planning | 4.0 Changes to Original Work Plan | 5.0 Sampling Activities | 6.0 Preparation of Iterim Cap Surface | 7.0 Intallation of the Geosynthetic Clay Barrier | 8.0 Placement of Geomembrane and Geonet | 9.0 Placement of Vegetative Support Zone | 10.0 Site Surface Water Controls | 11.0 Site Restoration | 12.0 Data Validation | Photos
4.2 Changes to Original Work Plan
As the remediation project proceeded, several changes to the work plan approach
were proposed to the government parties. Based on the acceptance of these
changes by the parties, the work plan approach was modified.
4.2.1 Further Delineation of PCB Contamination
In parallel with the remediation Viacom was conducting a subsurface investigation
program p, imarily in the southeast portion of the site. The data obtained during
these investigation activities suggested the configuration of the hot spot contours
could be better defined. The contours described in the SOW were based on 15
borings completed in 1996. As a result of this investigation a total of 92 additional
borings were completed in the southern portion of the landfill. Samples were taken
and analyzed for PCB contamination. The results more clearly defined the limits of
PCB contamination and the actual hot spot excavation. The additional borings were
used in conjunction with the original borings to guide the removal and disposition of
contaminated material. A complete description of the boring activities and results is
provided in the report "Delineation Borings in the Southern Portion of the Lemon
Lane Landfill" contained in Appendix A.
In Appendix A, Figures 5 and 8 identify the elevations at which excavation of TSCA
(hot spot material) contaminated material stopped. The information on these
drawings was used to guide the daily excavation activities. In grids F17, G17, H17
and in the southern half of F16, G16 and H16, the boring results were also the final
verification data. All other grids were post-excavation sampled to verify that the
clean criteria was meet.
4.2.2 Increased Perimeter Air Monitoring
The original work plan identified five locations where high volume air sampling units
were to be placed to monitor the air for PCB at the limits of the site. The proposed
locations are shown on Figure 1 of the LL WP Appendix E and in Figure 5 of this
report. The plan called for the down wind units to be analyzed on a 48-hour
turnaround time During the project there were occasions that the PCB level
exceeded the action level. As a result, several changes were made to the original
air monitoring plan. Variations of these changes occurred at various times during
the project. The changes included:
- Increasing the number of locations monitored and shifting monitor
locations based on excavation location (new locations shown on Figure 5).
- Daily analysis was changed to analyze all units or to analyze those next to
residents and the down wind units.
- Shorten the analysis turn around time from 48 to 24 hours.
The details of when these changes were implemented are described in Section 5 3
of this report.
4.2.3 Grid Verification Sampling
After the initial removal of contaminated materials the excavated surface was
sampled to verify that the clean criteria was meet. The verification sampling was to
consist of four samples being taken from a grid or a subgrid. These samples were to
be composited and the composite sample was to be analyzed for PCB level. In
most cases the four samples were not composited but analyzed individually. The
results of the individual samples were used to evaluate if the area sampled met the
clean criteria or required additional excavation.
The grid system used is represented on Figures 6, 8 and 9 of this report. The
lettered grids run east and west and the numbered grids run north and south. The
LL WP originally specified that the grids within the hot spot contours west of the
31011 00E survey coordinate line would be sampled on the basis of 100 ft. x 100 ft.
grid system. One sample was to be taken from each 50 ft. x 50 ft. subgrid and
composited. Instead the grid sampling was done either on 50 ft. x 50 ft. or 25 ft. x
25 ft. grids and samples prepared as described in the previous paragraph.
4.2.4 Site Control Procedures
A set of site controls were defined in the work plan that identified steps to be taken in
the event PCB action levels were exceeded at the high volume air samplers. When
PCB action levels were exceeded over a number of days, a shut down of site
operations occurred. The site operations and the site conditions to that point were
thoroughly reviewed during the shutdown. An analysis was conducted to determine
the potential causes of the action levels being exceeded. As a result of the review
and analysis, a revised set of site controls were developed for the excavation
process and material handling. These controls were imposed primarily to limit dust
and PCB vapor that could be generated during the remaining remediation activities.
A discussion of the shut down and revised controls is provided in Section 4.4.3.
4.3 Site Preparation
WRS and PSARA mobilized on site on April 17, 2000 and performed general site
preparation work through the week of May 8. In April 2000 the Sarah Elizabeth Frey
and the organization "Friends of the Woods" filed a lawsuit objecting to the remedy
chosen for the Lemon Lane site. In May 2000 they requested that the court to issue
an injunction and a temporary restraining order (TRO) to stop implementation of the
remedy. The removal of the interim cover and excavation of any material under the
interim cover was delayed until the court made a ruling on the request. This delayed
installation of the loadout scale, TSCA loadout pile and the decontamination areas,
which required the excavation and handling of material under the interim cap. The
court subsequently denied the request for the injunction and TROon May 16, 2000.
On May 17, 2000 the interim cap was removed and material under the cap was
excavated allowing the site preparation to continue.
4.3.1 General Site Preparation Activities
A site access road and stone paved staging area were constructed as shown in
Figure 2. The existing access road from Vernal Pike was widened and drainage
improvements were made. A water spray system was installed along the entrance
road to control dust. A truck turnaround loop was included as shown in Figure 2 to
provide truck access to the loadout pile and truck scale.
The loadout area was located within the exclusion zone and adjacent to the truck
scale. The loadout area was graded and lined with 40-mil plastic. The truck scale
was directly west of the loadout area. The scale was 35 ft. long and 10 ft. wide and
constructed on a concrete foundation. Tractor-trailer dump trucks were loaded while
positioned on the scale. A scale house was located just west of the scale. Located
in the scale house was a digital readout of the truck weight. The readout was used
by WRS personnel to direct the loading of the over-the-road trucks that transported
the contaminated solid waste to the TSCA landfill.
The office and equipment trailers were installed in the staging area. This area was
also used for material storage. A metered city water supply was installed and run to
the site from a fire hydrant at the northeast corner of the site, on Lemon Lane.
Limited clearing and grubbing was required around the perimeter of the interim
Hypalon cap to accommodate remediation and construction activities. Several large
trees were removed along the northern part of the site on property adjacent to the
landfill. The larger pieces of wood were cut and stacked and left for use by the
landowner as firewood. Small brush and trees~from around the perimeter of the site
were removed as necessary and chipped. The wood chips were stored on site and
used as an absorbent on the bottom of the rolloffs that were used to transport
capacitors to the TSCA incinerator.
Site survey control was established as discussed in Section 3.5. The borrow area
used as the source of clay to backfill excavations was located approximately 500 ft.
west of the staging area. The top layer of soil was scraped and stockpiled prior to
the start of excavation. This topsoil was used to restore the borrow area at the end
of the project. A dirt road was built between the borrow area and the site.
The perimeter fence line on the west side of the landfill was extended further west to
include the new access road and the staging area. Gates were installed across the
entrance road near the northwest corner of the site and the borrow area on the west.
A security checkpoint was established at the northwest entrance gate along the
access road off of Vernal Pike. A guard booth was placed at that location. A second
guard booth was set up on the northeastern fence line of the site. A guard service
was contracted to provide security 24 hours a day.
The same type of sediment control fence recommended by the Indiana Department
of Transportation was selected for use for this project. Sediment control fence was
installed around the perimeter of the site and around the borrow area where the
slope was away from the site. A trench was dug to anchor the bottom of the fence
into the soil.
A water treatment system was installed at the southwest corner of the site within the
fence line but outside of the exclusion zone. The location of the treatment system is
shown in Figure 2. The treatment system was built as described in the WP. The
system was installed to treat all water collected that came into contact with
contaminated waste and also water from the decontamination operations.
Five high volume air monitors were located at the perimeter of the site to monitor the
air at the fence line for PCB content. The locations were described in the Air
Monitoring Plan, Appendix E, of the LL WP. Two days of background samples were
taken on April 19 and 20 and analyzed prior to the start of excavation. Background
sample results are included in Table 5.
The initial health and safety (H&S) orientation for all Viacom, WRS and PSARA
personnel was conducted on May 1. All new workers arriving on site throughout the
project were required to attend a H&S orientation.
4.3.2 Site Preparation of Scale, Loadout, and Decontamination Areas
Part of the site preparation was the installations of scale, loadout and
decontamination areas. Installation of these areas was delayed until the
government parties provided approval of the LL WP. Approval was required
because waste was present in the areas and needed to be removed as part of the
construction. On May 17, after final approvals were obtained to begin excavation,
the interim cap was opened in the northwest. The waste under the Hypalon was
removed for consolidation and the resulting clay surfaces were sampled to insure
the clean criteria were met. The initial areas where the liner was removed were in
the northwest corner of the cap where the truck scale, TSCA loadout pile and the
decontamination pad were to be located. Also, the northwest corner of the cap was
uncovered to extend the access road to the truck scale. These areas are shown in
Figure 2, Site Layout. These areas were mainly outside of the limits of the hot spot
excavation contours. Waste under the interim cap in these areas was to be
removed and consolidated within the Limits of Consolidation (LOC).
The Hypalonliner and cushion sand were removed from the north central portion of
the interim cap to prepare the initial consolidation area inside the LOC. The waste
from the initial excavation areas would be consolidated in this location. After the
liner was peeled back, the granular cushion sand was removed down to within a few
inches of the underlying geotextile. Cushion sand was stockpiled for re-use in an
area to the southwest of the landfill within the security fence.
All waste outside of the LOC and under the interim cap was excavated down to
native soil and consolidated within the LOC. The residual cushion sand and the
underlying geotex+.ile were consolidated with the underlying waste. The native soil
under the excavated waste was sampled for verification as specified in the WP.
Verification sampling results after removal of visible waste in the northwest corner of
the cap revealed that the proposed location for the truck scales in C7 contained
PCBs above the clean up criteria. Subsequent delineation by hand auger and
machine borings revealed TSCA material to depths at or near bedrock. The quantity
of TSCA material requiring excavation from the grid containing the scales exceeded
the limited capacity of the loadout pile. Therefore the decision was made to
postpone excavation of this grid. The truck scales were relocated one grid to the
south, to C8 as shown on Figure 2. The loadout pile was also extended from D7 to
D8, adjacent to the truck scale. Verification sampling showed the new locations to
be clean. Grid C9 was excavated to complete the access road to the truck scales.
Portions of C9 were excavated to bedrock due to deep PCB contamination. The
scale foundation was installed and the scales were calibrated. A scale house was
installed next to the truck scale as shown in the site plan, Figure 2. The access
road to the scale was completed.
A personnel decontamination trailer was installed on the west side of the landfill,
south of the TSCA loadout pile. The trailer included personnel showers with a hot
water supply. Access to the exclusion zone was located between the loadout pad
and the decontamination trailer. These areas are identified on Figure 2. The
exclusion zone entrance included an equipment decontamination pad. Water from
the personnel decontamination trailer and the decontamination pad was collected in
a holding tank located adjacent to the personnel trailer. From the holding tank
contaminated water was pumped to the water treatment system. The capacitor
rolloffs were staged just north of the decon pad as shown on Figure 2. Several
capacitors were discovered and removed in the area excavated for installation of the
decontamination pad, grid C12.
4.4 Excavation Activities
As previously mentioned, there were three main areas of excavation related to the
rememdiation of the LL site. Waste that was previously shown to be clean and was
outside the new LOC was excavated and consolidated within the new LOC. A hot
spot area was specified in the work plan that required material to be excavated and
disposed of off site. This hot spot area was modified based on data from additional
borings completed during the remediation activity. As the excavations were
completed the remaining surfaces were sampled to determine if the surfaces met the
clean criteria for that area.
4.4.1 Consolidation Area
Waste outside of the hotspot contours that was shown by previous sampling not to
be hot spot material (PCB content less than100 ppm) was consolidated on site. In
these areas visible waste was excavated and removed down to native soil. Also,
material that required excavation based on verification sampling was consolidated if
the material met the consolidation criteria of the SOW. The removed material was
consolidated within the new LOC as shown in Figure 3. Prior to consolidation the
existing interim Hypalon cover was removed and the cushion soil was excavated
down to within a few inches of the underlying geotextile. Cushion soil was stockpiled
in an area southwest of the landfill for later reuse.
Consolidation started on the north central area within the LOG and was placed in lifts
approximately 18 in. thick. Each lift was compacted with a sheepsfoot compactor.
To help control air emissions the intermediate grades of consolidated material were
periodically covered with borrow clay. This was done in areas where consolidation
material was not actively being placed. The consolidation of waste material
continued until the approximate final landfill elevation was obtained. Colder
provided, in Figure 11 of the LL WP, an anticipated top of waste consolidation that
was used as a guide by WRS to place the consolidation materials.
4.4.2 Excavation and Loadout Of Material for Off-Site Disposal
Two waste streams were taken off site for disposal. One was contaminated landfill
material and soil with a PCB content greater than or equal to 50 ppm. The other
waste stream was whole capacitors that were buried within the excavated waste.
The contaminated material was either in the hot spot contour or identified based on
post-excavation verification sampling. The excavation of hot spot waste started in
the northwest and generally proceeded down the west to the southwest and then
across the south to the east edge of the site. Excavation was accomplished using a
track excavator. The excavator typically sat on top of the waste and excavated the
waste below, creating a vertical working face. The depth of the cut would generally
be the thickness of the hot spot waste. The excavator loaded off road articulating
dump trucks that would take the waste from the excavation to the TSCA loadout pile.
These dump trucks would generally sit at the bottom of the excavation to be loaded.
TSCA material was taken to the loadout area on the west side of the site. The
number of trucks loaded per day varied. A total of 3,093 trucks were loaded
containing TSCA waste with a total weight shipped of 80,097 tons. Table 4 provides
information on the days that trucks were loaded, the number of truck,, I`'adedeach
of these days, and associated net weights of material that were shipped to the EQ
Landfill in Belleville, Michigan for final disposal. The first trucks of TSCA material
were shipped to EQ on June 12, 2000 for disposal.
Capacitors were encountered during general waste excavation throughout the site.
When capacitors were encountered, a track excavator was used to uncover the
buried capacitors. The excavator removed the capacitors and placed them adjacent
to the excavation. Laborers then loaded the capacitors into the bucket of a front-end
loader. The loader transported the capacitors to 20-yard capacity roll off boxes that
were located near the exclusion zone entrance. Table 3 lists the shipments of
capacitors to the Onyx (formerly Chemical Waste Management) incus rater located
in Port Arthur, Texas. Two to three rolloffs were on site at any one time. As one
was filled, an empty was delivered and the filled one transported to Port Arthur. The
first shipment of capacitors to Onyx occurred on July 6, 2000.
The selected route for the filled trucks to follow from the site access road was left
onto Vernal Pike and then onto Route 37 on their way to the off site disposal
facilities.
4.4.3 Impact of Consolidation, Excavation and Loadout on Air Monitoring
Results
During the consolidation, excavation and loadout, perimeter air monitoring was
conducted to detect the PCBs levels at the fence line. On several occasions the
action levels for the perimeter air monitors were exceeded. In June and again in
July the action levels were exceeded on several consecutive days. In July when the
action levels were exceeded this caused the site operations to be Strut down. Prior to
restart of the site operations an addendum to the work plan was prepared that
described steps to be taken to control PCB emissions. This became Addendum #1
to the LL WP. This addendum was reviewed and approved by the government
parties. The following is a brief summary of the causes associated with the levels
being exceeded and the steps taken to lower the measured levels.
4.4.3.1 Operations Shutdown
A high air emission event occurred in early June during the excavating, and
consolidation of material in the north central portion of the LOO. A'. Serial was
consolidated in this area, air monitoring results slowly rose until results exceeded the
action level of 1000 ng/m3. On Friday, June 2, 2000, the southeast sample was
1611 ng/m3. By Monday, June 6, the southeast monitor result had inreased to
2066 ng/m3.
Response actions were immediately implemented to reduce the PCB air emissions.
The TSCA loadout pile was covered with plastic when inactive. Grids with
excavation in progress and exposed waste faces were also covered with plastic
when inactive. A thin soil cover was placed over the consolidated waste in inactive
portions of the LOC. Garden sprinklers were installed around the perimeter of the
TSCA pile to help control dust. These actions were completed by June 10. When
excavation restarted, PCB levels declined to below the action level of 1000 ng/m3.
In mid-July several concurrent site operations were in progress. Concurrent site
operations during this period of time included:
- Deep excavations of PCB contaminated soil along the western perimeter of the
landfill in grids C and D, 10 and 11. In some subgrids the excavations were to
bedrock, with free PCB product found at the bottom.
- Grids C, D, E/16, 17 in the southwest were being excavated and over 900
capacitors were recovered from these grids.
- Waste was excavated to depth of native soil in grids L, M, N. O/17, 18 in the
southeast. Approximately 165 capacitors were recovered from L17 on July 18.
- Between July 12 and 17 the Hypalon liner and bedding sand used for the interim
cap was stripped from approximately 60,000 square feet of ares along the south
of the site. This would represent the surface area of twenty-fou' 50 ft. square
grids. Later, when this area was excavated, most of the capacitors found at the
site were recovered from here
.
These concurrent operations resulted in large areas that had been excavated but not
backfilled. Most of the above listed activities were in highly contaminated areas,
areas with free PCB product, and/or large concentrations of capacitors. In most
completed excavation areas the bottoms of the excavations had been verified to
meet the clean criteria. However, a large sidewall surface area in the hot spot
contours remained exposed and contained visible capacitors and capacitor parts.
During these activities beginning on Thursday, July 13, 2000 and extending to
Tuesday, July 18, the site experienced six consecutive days during which the air
monitoring results again exceeded the action level of 1000 ng/m3. On July 17 the
southeast air result rose to the maximum site PUF level experience `] during the
project at 5630 ng/m3. Excavation operations were discontinued on I hursday,
July 20, when these air monitoring results were reported.
4.4.3.2 Application of Cover Material
As part of the shutdown of site operations, exposed areas were covered to help
control the emission of PCB contamination into the air. Several typt'S of cover were
placed over the exposed waste during the shutdown. Initially plastic. or stripped
bedding sand was used to cover the horizontal surfaces of the exc`'vation while
plastic was placed on sidewalls. Latex dust suppressants and hydomulch were
applied over exposed consolidation surfaces. Air monitoring results continued to be
elevated with these cover materials. Ultimately during the work stoppage all
excavation sidewalls and bottoms were covered with clean borrow clay
As part of the application of cover material a comparison was done i,` me field of
temperature rise under clear and heavy (4 mil reinforced) white plastic
Temperature under clear plastic rose significantly above ambient while temperatures
under thick white plastic rose very little. Although clay was used during the shut
down the heavy white plastic offered an alternative to clay once the operation restarted and daily cover was needed.
4.4.3.3 PCB Transport Mechanism
In order to restart operation some understanding of the causes of the high air
monitor results is required. The initial site controls focused on PCB air emission
being related to dust contaminated with PCBs. The traditional controls such as
spraying water on material as it was being excavated had limited effc ctiveness in
reducing the air results. A literature review was conducted of research and also
various experts were contacted regarding the properties of PCBs that relate to air
emissions. The review and discussions led to the belief that volatilization of PCBs
was a primary source of PCB causing high air monitoring results. It was determined
that high ambient air temperatures would increase the potential for volatilization.
High air temperatures were experienced during the elevated air results with daily
highs of eighty to ninety degrees. Exposed contaminated excavation surfaces both
bottoms and sidewalls would release volatilized PCB as the soil heated up.
Following this same reasoning another major contributor to PCB a,, e missions was
thought to be the release of PCB that was trapped under the Hypal`,n cover. The LL
site had a black Hypalon cover in place since 1987. The temperature under the
black cover was most likely elevated because of the black surface. I ice PCB vapor
was contained in the porous bedding sand below the cover and was trapped under
the Hypalon cover. This PCB trapped under the cover would have teen released
when the Hypalon and bedding sand was stripped. As described at~c~ve between
July 12 and 17 the Hypalon liner and bedding sand were stripped Am a large
highly contaminated area along the south of the site. By mid July, all but a very
small portion of the Hypalon had been stripped off of the site.
The cause of the high air monitor results and actions implemented to reduce the
levels are discussed more thoroughly.in the report "Review of Probable Causes of
Elevated PCB Emissions and Effectiveness of Mitigation Efforts" distributed to the
government parties on August 7 2000.
4.4.3.4 Plan for Restart and Measures Implemented
After considering all the potential causes for the high PCB air monitoring results
Viacom evaluated different operational alternatives that would prevent a recurrence
of high PCB air emissions. A restart plan was developed that addressed the
potential causes. The plan included implementing the following measures:
- Minimize the surface area of open excavation faces. Remove cover clay just
prior to excavation.
- Start with a low excavation rate and increase gradually while closely reviewing
and evaluating air monitoring results.
- Cover all excavations as soon as possible. Use clay cover or heavy white
plastic. Secure the edges of the white plastic with sandbags.
- Excavate TSCA in the coolest part of day. Start work at dawn.
- Minimize the quantity of TSCA waste in the loadout pile.
- Build a windscreen berm around the loadout pile using clean clay Have the
excavator sit on the clean clay berm of the windscreen to load trucks.
- Use water-misting system at the loadout pile and excavations to reduce
temperatures and reduce air borne dust.
- Remove capacitors from excavations as soon as possible. Place capacitors into
plastic bags as they are unearthed. Place the bagged capacitors in rolloffs that
have covers than seal.
To help evaluate the effectiveness of these controls three new neighborhood high
volume air monitors were also installed prior to the re-start of site operations. A
work plan addendum was prepared describing these controls and the installation of
additional monitors. The addendum was submitted to the government parties on
August 14 and discussed at the August 15 weekly project status me eting. The
government parties approved the Work Plan addendum and excavation operations
were restarted on August 16 2000. The Work Plan Addendum is included in this
final report as Appendix C. The site control requirements of this a`~›iendum were
implemented for hot spot excavation loadout of TSCA waste and re-excavations
that were required based on verification sampling to meet clean up criteria.
4.4.4 Achieving Clean Up Criteria
Figure 3 shows the excavation contours and the 25 partitioned areas that the LL site
was divided into for excavation and clean up verification. The hot spot excavation
contours were revised in some places based on the additional delineation boring
sampling that was performed during the remediation activities prior to excavation.
This was described in section 4.2.1. Once waste was removed from the areas
verification sampling was conducted to demonstrate that the remaining surface met
the clean up criteria. Various clean up criteria were specified for each area as
indicated in Table 1 of Appendix D of the LL WP. Clean up criteria varied depending
on whether the area was inside or outside the LOC. Areas outside the LOC varied
based on the future access to the area (inside or outside the fence) and whether the
area was considered residential or not. Each area had a criterion for each individual
grid as well as a criterion for the average of all grids within the area. In some cases
the arithmetic average criteria changes if clean cover is applied over the final excavated surface. In some cases areas outside the fence did not rig squire any
excavation to meet the clean up criteria based on pre-excavation sampling as
described in Appendix A of the LL WP.
Verification sampling criteria varied for the hot spot contours in gent Al as follows.
Excavated hot spot grids inside the LOC were cleaned so that each grid surface was
<100 ppm. This area was then eventually covered with the RCRA subtitle C cap.
Excavated grids which were inside the hot spot excavation contours but outside of
the final LOC had two levels of cleanup criteria to meet. First the bottom of the hot
spot contour (either as defined in the SOW or by additional borings) were sampled to
verify that the surface meet the <100 ppm clean up criterion. Material continued to
be removed based on analytical results until the cleanup criterion for that particular
area outside the RCRA cap was meet.
Verification sampling outside the hot spot contours and outside the LOC was
conducted after the visible waste was removed and native soil surface obtained.
Again material in this area continued to be removed as required by sample results
to meet the final cleanup criteria for that area.
The removal of PCB contaminated material to meet the clean up requirements for
the various areas within the LL Landfill site are described in the following sections.
The various areas are shown in Figure 3. All depths of excavations were referenced
from the original landfill surface. All material excavated from within the hotspot
contours was taken to the TSCA loadout pile for disposal. Any whole capacitors
were separated from the TSCA material and sent off for incineration Verification
sample results were used to determine whether material that needed to be
excavated was to be disposed of off site or could be consolidated on site.
Visual Standard
Waste that was to remain on site was subject to visual inspection by the Viacom
representative and the government party representatives. Visual inspection was
conducted at the surface of the hot spot contour within the LOC on' e the waste was
removed. Also all waste that was outside the LOC and was to be ~ consolidated was
inspected. Material that was to be consolidated on site was visually inspected for
whole capacitors capacitor parts and stained soil. Any observed W'ndin95 and
stained soil were removed prior to consolidation and taken to the 1 MA loadout pile
for subsequent off site disposal. Whole intact capacitors were removed and placed
in roll-off boxes for subsequent incineration.
If a large quantity of capacitors or capacitor windings were encounter red the
adjacent waste plus an additional bucket width of material was removed This was
done to determine if the concentration of capacitors or parts continued beyond the
initial excavation.
An inspection of the excavated surfaces was conducted jointly by thr Viacom
representative and the government oversite personnel to implement this visual
standard. A consensus between these two parties was achieved in each grid or
subgrid as to whether it was necessary to remove any additional material.
4.4.4.1 Areas Outside the Limits of Consolidation
Areas 17 & 20
The area outside the LOC on the north east and west are included in Areas 17 and
20. The boundary between Areas 17 and 20 is the position of the new fence line
that will be installed. Area 17 as shown on Figure 3 contains all three area inside the
existing fence line and outside the new fence line on the north and east of the LOC.
Area 20 is the area inside the new fence line but outside the LOC on the north west
and east. Area 20 therefore will have limited access as opposed to Area 17 which
will be outside of the new fence.
The clean up criteria specified for Area 17 is an arithmetic average elf ~ ppm with a
maximum individual grid result of 5 ppm. If ten inches of cover are added then the
average can be increased to 5 ppm. For Area 20 the limited access due to the
location of the final fence allowed the clean up criteria to be less stringent. An
arithmetic average of 10 ppm with a maximum individual grid result of 20 ppm is
required.
All of the grids in Area 17 and most of the grids in Area 20 were outside the hotspot
contours. The WP called for all the waste in the grids outside of the hotspot
contours to be excavated to the native soil and consolidated within thr LOC. The
remaining native soil surface was then to be sampled to verify that It met the clean
up criteria. As discussed in Section 4.3.2 the initial areas to be excavated were to
accommodate the loadout activities in the northwest. This excavation was
conducted in Area 17 and 20. As waste was removed and soil exposer d in the
remaining soil surface was sampled. Area 17 grid C7 where the t,~'r.k scale was to
be located was found to contain TSCA material based on verification sample
results. High PCB levels were discovered in several grids including 1:)5 D7 and
014 that are located along the east boundary of the landfill. To exam trite clean up in
grid D5 borings were completed to bedrock and the soil sampled. /\ppendix A
discusses the boring samples which were used to guide the excavation process.
Verification sample results are contained in Table 1.
The northwest corner of the hotspot contours was included in Area :0 as shown in
Figure 3. The depth of the hotspot contour in this area was specific ri Is 4 foot deep.
The material in this area was excavated and sent off site as TSCA Subgrids of C9
in the northwest corner of the hotspot contour were ultimately excav Ted to bedrock
in order to meet the clean up criteria.
Subgrids of C/D-10/1 1 and C12 in Area 20 along the western edge at the landfill
contained deep contamination. Subgrids in A20C11 and A20C12 At ret excavated to
bedrock at up to 25 foot below the original surface elevation. Two Rumples were
taken of the western wall of the C11 bedrock excavation. Analytical results for the
sidewall samples were obtained at 660 and 590 ppm. Additional material was
removed from the sidewall, which was then resampled at 4.8 ppm.
Groundwater with a heavy surface sheen was observed seeping into tooth the C11
and C12 bedrock excavations. Three foot of pea gravel was placed on top of the
bedrock and geotextile was placed over the gravel. The locations of these two
bedrock excavations were surveyed and are shown on Figure 6 as PZ-C and PZ-D.
The excavations were then backfilled to grade with clean clay from the borrow pit.
Initially these will be piezometer locations measuring water levels above bedrock.
At the end of the excavation phase the loadout pile, scales and truck road within
Area 17 and 20 were removed and resampled to verify these areas met the clean up
criteria. Most of the grids in Area 17 were cleaned up to BDL. The resulting average
for all the grids in Area 17 is 0.5 ppm. The resulting average for ail the grids in Area
20 is 1.5 ppm.
Areas Outside the Existing Fence on the North, East and West
The clean up criteria for the north, east and west perimeter areas outside the old
fence line is to achieve an arithmetic average of 2 ppm within each of the northern
perimeter areas, with a maximum individual grid result of 5 ppm. The delineation
results of the pre-excavation perimeter boring results, as presented in Appendix A of
the LL WP showed that most of the perimeter grids on the north east and west
outside of the fence line met the clean up criteria without any material removal
required. Only grids in four of the perimeter areas north of the old fence line
required excavation. These were Areas 5, 6, 8 and 9 and the grids requiring
excavation are shown on Figure 3.
Figure 3 of Appendix A of the LL WP shows the results of the perin,eter delineation
sampling. Grids D4, D3, J4 and J5 on Figure 3 had sample results .~t~'ve the clean
up criteria of 5 ppm. The highest sample result was 13.4 ppm in this 0 to 6 inch
sample of D4. These grids were excavated to remove the soil con~,~inir1g PCBs over
5 ppm and then sampled for verification of cleanup. The material ~ xc..~vated was
disposed of based on the delineation sample results. Material that Was equal to or
greater than 50 ppm PCB was excavated and transported to the Ft' COCA landfill
for disposal. Materials over the clean criteria but less than 50 ppm were excavated
and consolidated onsite under the RCRA C cap.
The pre-excavation delineation sampling showed that all the 0 to 6 and 6 to 12 inch
samples in Area 9, the Sexton property, were below the clean criteria. The SOW,
however, required as part of this delineation that one deep boring be placed in each
perimeter area. The individual deep boring drilled in the center of Area 9 showed a
slightly elevated PCB content of 5.7 ppm at the 36 to 48 inch depth Because of this
boring result additional boring sampling was performed in Area 9 just prior to the
remediafion. Two manual split-spoon borings were performed to depths of 4 ft. and
5 ft in grids M7 and M8 respectively. The boring results in grid M7 were all BDL.
The sample results for gridP9 indicated consolidation material from 0 to 2 foot. M7
was excavated to 2 foot and a volume 10x10x5-ft deep around the original Area 9
boring was removed. Verification results after excavation were BDL.
It had been demonstrated in the pre-excavation delineation sampling that the grids in
Area 11 meet the individual clean criteria of c 5 ppm and the average over the
surface was also less than the 2 ppm requirement. However Viacorn directed WRS
to remove the material in grid P9 since the PCB level was close to the 5 ppm limit.
The final grid sample result was BDL and the average for all the Area 11 grids was
less than 1 ppm.
The average verification sample results for Areas 5 6 8 and 9 were between 1.0
and 1.9 ppm as shown in Table 1.
Area 22
Area 22 includes the area in the south part of the landfill that is inside the hot spot
excavation contours but is outside of the LOC. It extends across the entire width of
the hot spot contour from the C grids in the southwest corner to the O grids in the
southeast corner as shown in Figure 3. The cleanup criteria for this area is 35 ppm
maximum for an individual grid with an average of all grids in the area less than 20 ppm. Ten
inches of clean soil cover is required for Individual grids that are more than 5 ppm and are
accessible to people (outside the final fence line)
As discussed in Section 4.5 excavation areas that were inside the excavation
contours but outside of the final LOC had two levels of cleanup criteriap to meet. The
grids in Area 22 south of the LOC were to be excavated to the contours and then
sampled to determine that TSCA material at the bottom of the contours had been
removed. Any remaining wastes that meet the consolidation criteria were then
excavated and consolidated within the LOC. The remaining clay surface with a PCB
content more than 35 ppm was consolidated if the PCB level meet the consolitation criteria.
The final excavated surface was sampled to verify the clean criterion was met.
To better define the PCB content beyond the contours there was In interest in
installing borings to sample this material prior to contour excavation. Given that
borings were to be installed this provided the opportunity to better define the PCB
content within the contours in advance of excavation. The LL SOW states that CBS
may segregate materials within the excavation boundaries that it has reason to
believe are not contaminated above 50 ppm for consolidation onsite.
"Demonstration that the materials are less than 50 ppm through sampling" is called
for. Borings were performed in the southeast grids of Area 22 to further delineate
this area for segregation. A revised excavation plan based on the southeast borings
was agreed to at the July 6 meeting between Viacom and the government party
representatives. Appendix A discusses the southeast borings and the resulting
revised excavation plan. During the week of July 10, excavation began in the
southeast part of Area 22.
The excavation in the Southeast area began in grids MNO/17-18. Except for the
northeast part of M17, all of these grids are outside of the LOC in Area 22. The
sand overburden was removed to just above the geotextile. The residual sand, the
geotextile and the underlying waste was excavated down to the depth of the native
soil and was sent off site as TSCA. The southeast boring results had shown that all
the waste in these grids, down to native soil, was TSCA material. The data from the
borings had also shown that an additional one foot of the native soil in N17, and two
foot in N18 and 3 foot in J19 should be disposed of as TSCA. The remaining native
soil, down to the excavation contours, was shown by the borings to be suitable for
consolidation on site or had low enough PCB levels to remain in place.
In some cases the excavation of the underlying clean native soil down to the
excavation contours required the soil to be replaced with clean backfill to build the
area back up to the final construction elevations required. As an alternative to
excavating, consolidating and replacing clean soil with borrow clay, the government
parties agreed to allow the clean native soil to be left in place. In order to leave the
clean native soil in place, the soil was verified clean on a subgrid basis (i.e. center of
each 25-ft x 25-ft grid) from the top of the final excavation to a depth 6 inches deeper
than the applicable contour. Samples were collected at 1-foot intervals in each
subgrid. These sample results are reported by sample depth interval in the grid
sample log, Table 2.
By the time of the work stoppage on July 20, grids L17 and MNO/1~-18 had been
stripped of waste, down to the depth of the native soil. Excavation resumed on
August 16 after the work stoppage, as discussed above in Section ~ 2 4. Work
resumed in the southwest corner of the landfill in grids CD/18 of Area 22. The
remaining grids in areas 22 and 24 were excavated moving from west to east.
Capacitors continued to be recovered in this area after work resunn~d, especially
along the south bank of the landfill in grid row 18 and 19 The measures that were
agreed to for restarting the excavation operations were implements d A dedicated
crew batched the capacitors as soon as they were uncovered. Also the water
misting system was employed to reduce temperatures and prevent Lust locally in the
excavation area.
The Area 22 grids west of the 3101100E line were excavated per the contours
specified in the work plan. In some of these grids waste existed beyond the bottom
of the contours. This waste was sampled and characterized for consolidation or
disposal. If the analytical result was less than 50 ppm the waste we consolidated
into the LOC. If it was greater than or equal to 50 ppm, the waste we sent off as
TSCA. Once the waste was removed to the depth of the native soil, a verification
sample was taken in the native soil to determine if it met the cleanup criteria of less than 35
ppm and could remain. Table 2 contains the results of the waste characterization as
well as the verification sample results.
Excavation of the grids in Area 22, east of the 31011 DOE line, was started during the
week of September 18. These grids were excavated according to the southeast
boring agreement as discussed in Appendix A. Most of the grids in this part of Area
22 had the waste excavated down to the native soil as TSCA. Additional soil was
removed as TSCA based on the boring data. As discussed above, clean native soil
above the contours was confirmed clean and left in place rather than excavate and
re-fill the area. Figure 4 shows four individual subgrids, N18SE, N18NE, 018SW
and J19SE, which are located outside of the new fence. These suhgrids met the
clean criteria but had analytical results greater than5 ppm. A minimum of ten inches of clean
soil cover was placed over the subgrids.
The southeast boring agreement also specifies three grids in Area 22, 118, J18 and
K19 which were to have additional subgrid borings performed to delineate the waste
for disposal or consolidation. The original boring in the center of these grids resulted
in waste samples that were mostly clean. Appendix A discusses the borings and the
sampling performed in grids J18 and K19 for delineation.
Grids MNO/19-20 in the southeast corner of the landfill were specified for excavation
to bedrock per the southeast boring results. These grids were excavated to bedrock
during the week of October 9 and consequently no verification sampling was
performed because of the bedrock.
LF6 Deep Bedrock Excavation
As discussed in Section 3.4, LF6 was installed as part of the southwest subsurface
investigation. PCB free liquid product had been recovered from monitoring well LF6
in the past. LF6 is located at the intersection of two fracture traces through the
bedrock in grid M20 in Area 22. Based on the southeast boring program discussed
in Appendix A, M20 was one of the grids to be excavated to bedrock.
In an attempt to locate the source of PCB that had been observed in I F6, Viacom
had the excavation taken through the bedrock to the bottom of the I F6 well. The
total depth of excavation from the previous surface of the interim calf was 37 feet to
an elevation of 839.5 feet ASL. Some PCB staining was discovered on the bedrock
that was removed. A large clay filled void, about 9 ft. high existed at tile bottom of
the excavation. Water with an oil sheen was observed to collect at tiffs bottom of the
hole.
The oil stained rock and the clay from the bottom of the excavation were sent off to
TSCA. The government parties agreed to allow the unstained rock to be cleaned
dirt and consolidated under the cap. The excavated hole was filled with about
15 feet of pea gravel. A layer of geotextile was placed over the gravel and covert.
with clay to grade.
South Perimeter Areas 13, 14 and 15
Perimeter grids along the railroad tracks from 119/20 to 020 in areas 13 to 15 wer
to be excavated based on perimeter delineation results presented in Appendix A
the LL WP. Cleanup criteria for the southern perimeter, outside of the old fence li
was a maximum of 35 ppm PCB for individual grids with an average of all grids in
area to be < 20 ppm if ten inches of cover are placed over the grids.
During the week of October 9, the fence was removed and the area to the railroac
tracks was cleared. Grids L20 through 020 (Areas 14 and 15) were excavated pE
the plan and verified clean. Ten inches of clean cover was placed over these grid
The individual grid verification sample results and the average are listed in Table
Per the access agreement with CSX Transportation, the owner of the railroad, a
representative from CSX was present to observe the work in the area along the
railroad tracks. The CSX representative expressed concern about possibly
undermining the rail bed foundation by digging the embankment and riprap that
supports the rail bed ballast in grids 120 and J20. Excavating these two perimeter
grids would remove some of the foundation for the slope of the railroad bed. Digs
to the initially planned depths in the grids further east was not a problem since the
soil elevation was higher in that area and excavation would not impact the critical
slope of the railroad bed. This issue was discussed at the October 11 meeting wi
the government representatives. There was agreement at this meeting not to
excavate grids 120 and J20 and to allow Viacom to cover the these two perimeter
grids with one foot of compacted clay. A minimum of one foot of clay was
compacted over these grids. All the perimeter grids were then covered with topsc
and seeded. In the future, if the railroad tracks are abandoned, Viacom in
conjunction with the government parties will evaluate the circumstances related tc
the contaminated material remaining in grids 120 and J20. Based on this evaluation
a determination will be made as to what action is appropriate.
4.4.4.2 Hot Spot Grids Within the Limits of Consolidation
Area 21 (SB08)
Area 21 was a 25 ft. by 25 ft. square around soil boring SB08 and was within the
consolidation area. Boring SB08 was a hot spot area based on sample results
obtained during the 1996 soil borings investigation. The excavation contours
specified an initial excavation of four feet in this area, based on the 1996 borings.
The visual standard was used in inspections of the sidewalls and bottom of the
excavation to determine if any additional excavation was required. Ultimately
Area 21 was excavated to an eight-foot depth to obtain a visually clean bottom. The
average verification results for area 21 was 7.2 ppm compared to an allowable
average of 50 ppm.
Capacitors were discovered in the west sidewall of Area 21. Based on the visual
standard, the west sidewall of Area 21 was extended out about 60 feet at a depth of
5 to 7 feet. A total of 117 capacitors were recovered from Area 21 and the west
extension. Consolidation material was placed the excavated area after the clean
up was completed.
Area 23
Area 23 is the area east of the 3101100E line and inside the LOC. Excavation
began in this area during the week of July 10 when the waste was excavated in grids
M17 and L17 to native soil depth per the southeast borings agreement as discussed
in Appendix A. A cache of capacitors was recovered in L17. Area 23 was
essentially completed on October 3. Verification sampling results are shown in
Table 2 and Figure 4. This area was covered with consolidation material.
Area 24
Area 24 consists of the hot spot contours to the west of the 3101100E line (referred
to as the 5300E grid line in the SOW), which are contained within the LOC. The
northern grids of this area were excavated first. These grids were all within the four-
foot excavation contours. The excavation proceeded south within Area 24 where the
deeper excavation contours were located from 6 to 12 feet deep. A 30 foot wide
strip running north to south within grids G9 to G15, on the east side of this area was
left in place to accommodate a truck access road. This haul road was constructed
for use by the onsite TSCA trucks to operate between the southern excavations and
the loadout pile.
The SOW allowed verification to be performed in Area 24 using 100 square foot
grids. It was agreed with the government representatives that verification would be
performed in 50 ft. grids instead of 100 ft. grids. This minimized the surface that was
exposed during excavation. Reducing the sample area also provided more
representative verification results.
Excavation in CD/16-17 started during the week of July 3. Excavation of these grids
resulted in the discovery of another large cache of capacitors. Over 400 capacitors
were recovered from these grids. The first rolloff of capacitors was shipped to the
Onyx TSCA incinerator on July 6, 2000. A cache of non-friable asbestos tiles was
recovered in grids C16/17. Approval was received from EQ to ship this material with
the other TSCA waste. An asbestos awareness-training course was given to the
workers handling this material on July 12. The transits tiles were excavated and
shipped to EQ during the week of July 16.
During the week of August 21 the subgrids in grids FGH/16-17 were bored and
sampled to better delineate these grids as discussed in Appendix A. Excavation of
these grids proceeded per the boring sample results as agreed to with the
government representatives at the August 15 weekly meeting. Depth intervals that
contained less than 100 ppm PCB were consolidated. The average for Area 24 was
maintained below 50 ppm. Excavation stopped at the top of the first depth interval
sample below 100 ppm that was not underlain by another layer greater than
100 ppm. This depth interval sample was regarded as the grid verification sample
and no further sampling was performed.
During the week of September 11th the grids containing the onsite TSCA haul road
from G9-15 and F9 were excavated and confirmed clean. The TSCA excavation in
Area 24 for the contours west of the 3101100E line was completed at this time.
Area 25 - North Face Sidewall Excavation
The SOW required that the north sidewall of the hot spot excavation east of the
3101100E line be sampled to determine if PCB contamination extended north. This
four foot sidewall was sampled in grids 116 through M16.
The SOW called for four grab samples to be taken along each 50 foot sidewall grid
and composited for verification of that 50 foot length of sidewall. This was modified
in the approved work plan to allow two column samples, 25 feet apart, to be taken
along the sidewall for each 50 foot grid. A column sample was not composited with
another column but was sampled and analyzed separately. The full length of each
column sample was homogenized and a representative sample taken. In addition,
this sampling procedure was further modified in the field to sample only waste in the
O to 4 foot sidewall depth and not to include any clay fill material in the sample that
was part of the interim cover.
The work plan further allowed that each composite column sample could be used
separately to verify each 25-foot length of sidewall. In each 50-foot grid two sidewall
samples were obtained, an east and a west sample. The cleanup criterion for each
individual sidewall sample was less than 100 ppm PCB with the average of all final sidewall
samples to be less than 50 ppm.
The initial sidewall sampling along the north excavation face occurred over the
sidewall in grids L and M on July 27. Results for all 4 samples were >100 ppm.
During the week of September 11, test pits were dug to allow sidewall sampling to
be done in i, J and K-16. Two samples per grid were taken of the exposed waste to
the depth of the four-foot contour. Results of the sidewall samples were >100 ppm
in 5 of 6 samples. As a result, the sidewall was excavated back to the north about 6
to 8 feet in 1, J. and K-16 and resampled during the week of September 18. Sidewall
samples continued to not pass the clean criteria.
Eight test pits were dug in grids K-west, L and M to expedite identifying the northern
extent of any waste that was >100 ppm. In addition, on October 1 and 2, borings
were drilled in 1, J. K, L, M-14 to further facilitate the investigation. Waste material
from the boring to the depth of the four-foot contour was composited for each
subgrid. Boring continued north until a clean boring location was established for
each lettered subgrid going north. During the week of October 2, the government
parties allowed all the subgrids to be excavated to the location of the clean borings.
After excavation at the clean boring location an inspection per the visual standard
was conducted. No further verification sampling was required.
During this same time, City of Bloomington Utilities (CBU) resampled the sidewall in
the l-west (IW) subgrid in the north sidewall excavation. The initial sample result
was 41 ppm from the initial test pit sampling event on September 18. The validity of
the September 18 sample was questioned since the 0 to 4 foot composite sample
contained mainly clay fill, rather than waste. CBU took two sidewall samples in the
IW excavation, one from the south facing sidewall and the other from the east facing
sidewall. Both samples were determined to be above the clean up criteria. The
sidewall in IW was subsequently excavated past the east facing sidewall sampling
location to a point north of that sampled by CBU and resampled. The new sidewall
was then confirmed clean at 39 ppm.
Sample results for all the sidewall sampling and the average of all the clean
verification samples are contained in Tables 1 and 2. The final perimeter of the
sidewall excavation is shown in Figure 4.
4.5 Water Collection and Treatment
All.excavations and consolidation areas were protected by berms. The berms were
to limit run-on water and contain run-off water within the contaminated areas.
Approximately 35 batches of contact water were treated during the course of the
project. A total of 865,000 gallons of water were collected and treated on site.
Table 6 lists the individual batches of water treated, the sample result of the
verification sample taken before the water was released and the total gallons of
water treated.
The treatment system is described in Section 3.2.7 of the LL WP. Figure 2 of this
report shows the location and arrangement of the equipment as installed in the field.
Water collected and treated was either discharged to Sargent's Pond or used for
dust control within the exclusion zone. At the end of the project all the pool liners,
filter media, and carbon were disposed of as TSCA material.
|