COPA Home

Lemon Lane Final Report
June, 2001

1.0 Introduction | 2.0 Site Description and History | 3.0 Remediation Planning | 4.0 Changes to Original Work Plan | 5.0 Sampling Activities | 6.0 Preparation of Iterim Cap Surface | 7.0 Intallation of the Geosynthetic Clay Barrier | 8.0 Placement of Geomembrane and Geonet | 9.0 Placement of Vegetative Support Zone | 10.0 Site Surface Water Controls | 11.0 Site Restoration | 12.0 Data Validation | Photos

11.0 SITE RESTORATION

11.1 Soil Preparation and Seeding

The thickness of clean topsoil over the site typically ranged between 10 to 12 inches. Preparation of the topsoil surface for seeding consisted of back dragging the surface with the dozer or blading with a motor grader. The topsoil provides a clean cover over areas outside the cap to support meeting any of the cleanup requirements in these areas. Placement of the topsoil layer on the cap surface and over adjacent areas outside the perimeter channels occurred in late November through early December. This time frame was well beyond the typical fall planting period for Indiana. Once it became obvious that the schedule for planting would be this late, winter cover options were investigated. Contact was made with commercial landscapers, a local government park maintenance district and a hydromulch equipment vendor to determine the best winter cover composition and method for application. Through these discussions, it was determined that a thick layer of hydromulch mixed with seed and fertilizer would provide a stable cover for the winter. With the seed and fertilizer included, this approach would provide the opportunity for grass to start growing at the earliest possible time in the spring. This technique is used by golf course and road projects to winter soil surfaces.

A seed mixture of 80% fescue and 20% rye was used with a fertilizer mix of 18-24-12. The application rate per acre was as follows:

  • 3000 pounds of mulch
  • 300 pounds of seed
  • 200 pounds of fertilizer
  • 60 pounds of tackifier
  • 40 pounds of polymer
The mulch was composed of 100% wood fiber. The tackifier provided a bonding agent to hold the wood fibers together. The polymer works in conjunction with the tackifier to improve bonding of the tackifier. The polymer also helps to hold moisture to promote seed growth by releasing the moisture as needed. The polymer will also continue to reabsorb and release moisture for several years further supporting vegetation.

Two hydromulch machines (600 gallon and 1000 gallon units) were used to spray on the application of this mixture. Typically three passes over an area achieved the specified application rate. Water used in the mixture was obtained from the fire hydrant located at the northeast corner of the site. The mixture was applied to the cap surface and all disturbed surfaces within the old fence line that were not covered with riprap. Application of the hydromulch was completed on December 3, 2000.

11.2 Erosion Control

The hydormulch mixture was used to provide a majority of the erosion control. On the steeper slopes erosion control mat was used in conjunction with the mulch to insure the maximum erosion control was in place. The mat was a biodegradable material that will maintain control characteristics for 12 to 18 months.

In addition to the erosion control mat, silt fence was also installed at various locations where slope erosion could potentially impact the perimeter channel or where slopes tended to be long. Along the perimeter channel silt fence was installed on the inside and outside perimeter where the slopes were steep and drained toward the channel. On the cap surface silt fence was placed along the 882 ft. contour line This is the approximate location where the slopes of the landfill cap begin to increase as shown in Figure 8. All silt fencing was installed by placing the bottom edge in a shallow trench to anchor this edge to the soil surface.

11.3 Borrow Area Restoration

During the remediation and construction of the cap, soil for backfill and grading was obtained from the borrow area located just to the west of the landfill site. The surface was initially scraped to remove the topsoil which was stockpiled in the borrow area. Once excavation of the borrow soil was completed, all slopes created during the removal were graded to be approximately 3:1. Any large stones encountered during the excavation of borrow material were buried in the deep portions of the borrow area. Grading was done with the existing material to provide drainage and eliminate ponding. The final surface of the borrow area was contoured to re-establish the original drainage locations and directions. Topsoil was taken from the stockpile and spread over the surface of the borrow area. The topsoil was covered with hydromulch using the same procedure and mixture as previously described for the cap surface. Silt fencing was installed to the southwest of Sargent's Pond to limit the potential of sediment being carried into the pond from the borrow area.

11.4 Completion of Piezometers at Surface of Soil Cover

Weather became a factor toward the end of the construction activities in December at the LL site. The weather prohibited the completion of the surface details for the six new piezometers. The concrete pad around the riser pipe and the locking cap assembly will be installed in the spring of 2001.

11.5 Natural Gas Line Installation

Paralleling the old fence along the south and a portion of the east was a natural gas pipeline buried some three to five feet deep. The gas company abandoned the portion of the pipe that was within the old fence line of the landfill. During the excavation to remove the PCB contaminated materials, the abandoned pipe was removed.

After the area was verified clean and backfilled with clean soil the gas company installation contractor returned to replace and re-connect the gas line. The new location follows closely the location of the original line. The location of the new gas line was surveyed and this information is presented on Figure 8. The new fence line will be located so that access to the gas line for future maintenance is outside the fence.

11.6 Cross Section of the Completed Site

The final as-built configuration of the landfill is shown in cross-section in Figure 11. This figure shows the approximate original ground surface north to south, the approximate thickness of the consolidated waste materials, and the individual components of the cap. This figure also shows the general as-built slope profiles, constructed surface drains and other features, but does not show the bottom of the waste excavation. The bottom of waste at all locations outside the LOO was a visual determination that was subsequently verified by post-excavation sampling and analysis.

11.7 Permanent Survey Benchmarks

Permanent survey benchmarks were established as survey control points by SNA at locations outside the cap at the LL Site. A table on Figure 9 provides the northing, Casting and elevation for each control point. These benchmarks may be used to establish coordinate and elevation control for the purpose of future cap monitoring work that may be performed.

1 1.8 Demobilization

A preliminary site walk through with WRS, Viacom, PSARA and the government parties was conducted on November 14, 2000. Three issues were raised. These included placing erosion control along the railroad embankment in the southwest, cleaning the road surface on Gray Street and installation of the fence along the railroad track. At the time the hydromulch was placed erosion control mat was installed on the railroad embankment. Cleaning of Gray Street was increased to minimize the soil that collected on the surface from the truck traffic coming of the cap. The security fence was to be installed when weather permitted. The proposed layout of the fence is shown in Figure 8 with maintenance equipment access through gates located on the east and northwest of the cap perimeter.

The final site walk through was conducted on December 6, 2000, with the same group of people as the preliminary walk through. No issues were raised by any of the members of the government parties. The condition of the site met with their collective approval.

Demobilization of the last of the trailers and equipment occurred during the week of December 10, 2000. The last subcontractor, PSARA, left the site on December 15, 2000.


Warning! Eat no fish from Clear Creek, Pleasant Run, Salt or Richland Creeks.

Home
COPA

For more info, e-mail info@copa.org.
Copyright © 1990-2002 COPA, Inc. All rights reserved.
See legal page for terms of use and disclaimers.
All trademarks belong to their respective owners.