COPA Home

Lemon Lane Final Report
June, 2001

1.0 Introduction | 2.0 Site Description and History | 3.0 Remediation Planning | 4.0 Changes to Original Work Plan | 5.0 Sampling Activities | 6.0 Preparation of Iterim Cap Surface | 7.0 Intallation of the Geosynthetic Clay Barrier | 8.0 Placement of Geomembrane and Geonet | 9.0 Placement of Vegetative Support Zone | 10.0 Site Surface Water Controls | 11.0 Site Restoration | 12.0 Data Validation | Photos

10.0 SITE SURFACE WATER CONTROLS

10.1 Perimeter Channels

A perimeter channel was constructed beyond the LOC to control water flow associated with the cap. As mentioned previously, water that collects in the geocomposite drainage layer discharges into the perimeter channel. Also, surface run-on and run-off water has been directed to the perimeter channel. Surfaces outside the channels were graded so that a majority of the surface water would drain into the channel. Soil from the grading was used as cover soil on the cap or as fill to shape areas outside the cap. All areas on the cap and outside the perimeter channel were covered with 6 to 10 inches of topsoil after final grading.

Soil excavated from the channels was used as backfill outside the LOC and as fill to shape the western bench between the LOC and the retention pond. Bedrock was encountered while excavating a portion of the southeast channel and in the west at the entrance to the retention pond. A hydraulic ram was used to remove the bedrock. Due to this bedrock, the southeast channel was moved slightly further south than the Final Cap Design Report drawings show. This helped to limit the quantity of bedrock that needed to be moved. Backfill was placed over the bedrock and compacted. During construction, the soil associated with the perimeter channel was compaction tested along the length of the channel by the Thelen Associates representative. The results of the tests are provided in the PSARA portion of Appendix G. After excavation the channels were lined with a non-woven geotextile. The geomembrane lining from the cap was extended through the bottom of the channel and anchored at the outside perimeter of the channel. The surface of the geomebrane was covered with a layer of non-woven geotextile prior to placing the riprap in the channel. The perimeter channels were constructed as presented in the Colder Final Cap Design Report. The high point of the channel is located on the east side of the site. From that point water flows around the south or north of the landfill to the retention pond located on the southwest corner of the site. The final as-built configuration of the surface water control system around the RCRA cap covering the LL consolidation material is shown on Figure 8.

10.2 Retention Pond and Subsurface Drainage

Water collected in the perimeter channel is directed to the retention pond at the southwest of the site. The retention pond was excavated into the native clay at this location. This clay was used as backfill along the south of the site between the railroad tracks and the LOC. The slope of the west bank of the retention pond was changed from 5:1 to 3:1, limiting the quantity of soil to be excavated but still providing a maintainable slope.

Construction of the pond is similar to the perimeter channels, with the bottom of the pond covered first with non-woven geotextile, then seamed geomebrane and another layer of non-woven geotextile. The geosynthetics are covered by riprap down the center and vegetative cover soil over the remainder of the bottom and side slopes. The geomembrane for the pond was double fusion welded to the geomembrane coming off the cap on the east side of the pond. This essentially made one continuous piece from the cap across the bench on the east through the pond and up the west side of the pond. The geomebrane was placed in an anchor trench along the south and west perimeter of the pond. The geosynthetics were placed over the clay bottom to limit the possibility of water piping into the soil and eventually causing macro-pores in this area.

Water can drain from the pond by way of a drainage structure located at the north end of the pond. The structure outlet is to a 24 inch reinforced concrete pipe that was placed underground and drains to Sargent's Pond. Water can enter the structure in two ways. Typically water will enter the three 3 inch diameter holes near the base of the structure. These holes will drain the water from the pond at a controlled rate, thus limiting the water flow rate to Sargent's pond. The other method to drain the retention pond is through the 3 ft. x 4 ft. opening at the top of the structure. In the event of heavy rains or if the 3 inch diameter holes get blocked and the level of the retention pond reaches the top of the structure, the opening at the top will quickly drain water. The arrangement of the drainage structure that was installed varied from the proposed structure shown in the Colder Final Cap Design Report. The change reduced the amount of standing water that would remain in the pond by raising the elevation of the bottom of the structure. Drawings 6, 9 and 10 of the Design Report were revised to represent the final arrangement. These drawings are presented in Appendix J.

As mentioned above, the outlet of the 24 inch concrete pipe was at the edge of Sargent's Pond. An outlet structure was constructed to minimize erosion at the end of the pipe and to drain the water to the pond. The structure consisted of a flared end to the 24 inch concrete pipe, a Reno mattress and riprap.

The pond is designed to retain approximately 82% of a 10 year, 24 hour storm while the three 3 inch diameter holes are functioning to drain water during the storm event. The base of the drainage structure where the three drainage holes are located is covered with riprap. The riprap will help keep debris from closing off the holes. The function of the three holes is to limit the rate at which water drains to Sargent's Pond. Limiting the rate to Sargent's Pond will allow the natural drainage of Sargent's Pond to function.

10.3 Surface Drainage Outside Perimeter Channels

Prior to the remediation activities during heavy rains water ponded on Lemon Lane road at the northeast corner of the site. As part of the final grading beyond the perimeter channel, a swale was cut from the edge of the road to the eastern perimeter channel. The cold and snowy conditions in December, at the time of this work, limited what could be done to construct the swale. The swale and the area adjacent to the swale were covered with hydromulch that included seed and fertilizer. The swale was also covered with a layer of erosion mat. Once spring comes the area will be reworked as needed to improve the integrity of the swale.

As shown on the drawings in the Final Cap Design Report, a V-ditch was to be constructed in the southeast along the old fence line. The V-ditch was not constructed. Originally the V-ditch was to collect run on water from the eastern side of the site and from the railroad embankment on the south. Several factors influenced the decision to eliminate the ditch. The slope of the drainage area collected by the V-ditch along the railroad tracks was minimal. The volume of water expected from the east was also minimal. In the final cap design drawings the slope paralleled the perimeter channel for a distance before water flowed into the perimeter channel. A gradual slope was developed to flow directly toward the perimeter ditch during the final overall grading of the surface in the southeast.


Warning! Eat no fish from Clear Creek, Pleasant Run, Salt or Richland Creeks.

Home
COPA

For more info, e-mail info@copa.org.
Copyright © 1990-2002 COPA, Inc. All rights reserved.
See legal page for terms of use and disclaimers.
All trademarks belong to their respective owners.