CIC
May 4, 1999
Winston-Thomas
- Cleanup is 2/3 done at Tertiary Lagoon
- 1 ppm goal for cleanup , being met.
- EPA is doing split samples with Westinghouse, no problems.
- Boring samples in berms and abandoned creek bed.
- Fall 99 completion date.
- CBS must submit final
Neal's Dump
- Final seeding done - finished site last fall
- Groundwater monitoring plan in revision
- Site is done and EPA will be asking for removal from NPL this summer.
Lemon Lane
- Source control remedy out for public comment this summer or fall.
- CBS is looking for alternative methods for Lemon Lane conduit study.
- EPA issued administrative order on consent for CBS to cleanup Griffin property in June.
- Substantial Endangerment of Lemon Lane - Protective Remedy.
IC Springs
- Design is completed for plant
- Now a $5-6 million dollar project
- Land is cleared and ready to build foundations.
- May 1, 2000 completion date.
- Project stretched over 2 years for financial reasons.
- Backup generators will cost $300,000.
Bennett's Dump
Work to begin in late June, 1999
CBS will do additional sampling
Statement of work being negotiated
Additional contaminants found- Buried Drums
CBS does not want to deal with them, they did not put them there.
Neal's Landfill
- Mobilization has begun
- Interim Cap this fall with final RCRA cap next spring 2000.
- EPA position is that additional water and sediment treatment is needed.
- CBS' legal position is that they have met the orders in the Consent Decree, and do not have to do further water treatment.
- City, County and State were against moving Neals to Bottom Rd, where a RCRA liner could be installed. This is why Neals does not have a liner. There will be PCBs being released through the karst for many years, so water treatment will be needed anyway.
- Next phase is to deal with water treatment.
- EPA will pay for water treatment if CBS will not, and then sue to recover costs under Superfund.
Drainage Board has plan
Started removal on north side of landfill - 300 mostly intact capacitors removed to date.
Conard's Farm to supply borrow dirts.
Tire shredder will be brought in for the tires.
Tires were concentrated in the north area. If they are suspected of PCB contamination, they will not be shredded.
Cost Recovery, Water Treatment, Sediment Removal are all issues to be worked out.
Water Baseline sampling started.
Tetra Tech historical data report in process.
More data needed before decisions can be made about water treatment.
|