Bennett's Quarry

Weekly Progress Status Report

October 26 thru November 1, 1999

This report is intended to provide a weekly project update regarding the major developments for the remediation work at Bennett's Quarry. Included are progress updates, sample analytical results, schedule updates, waste shipping information and field change decisions. Complete sampling logs, shipping logs and air monitoring and meteorological data logs are available at the site. .

Bennett's Quarry Project Site Activities

Bennett's Quarry Planned Site Activities

November 2 - November 7, 1999

Comments or questions regarding this report should be directed to Jim Patrick on 812-334-0030 or Mike Hessling on 812-332-1240 or Ray Taylor on 412-642-2549.